Environmental approval grantedIndustry · Tumakuru, Karnataka

Increase in Production Capacity of Induction Furnace Product - Steel Billets From 29,988 Tpa to 2,10,000 Tpa, Rolling Mill Product - Narrow Strip /Rolled Products From 29,904 Tpa to 2,10,000 Tpa With Additional New Pipe Mill Product- Ms Pipe of Capacity 2,10,000 Tpa by M/S. Khayati Steel Industries PVT LTD

Increase in Production Capacity of Induction Furnace Product - Steel Billets From 29,988 Tpa to 2,10,000 Tpa, Rolling Mill Product - Narrow Strip /Rolled Products From 29,904 Tpa to 2,10,000 Tpa With Additional New Pipe Mill Product- Ms Pipe of Capacity 2,10,000 Tpa by M/S. Khayati Steel Industries PVT LTD is an approved industrial project in Nagenahalli, Tumakuru, Karnataka. The site covers 4.9 acres. Its stated project cost is ₹108.6 crore. As of 27 Nov 2026, its status is “Environmental approval granted” (since 15 Sept 2023).

See it on the live map All projects in Tumakuru

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Quick answers

What is this project?

Increase in Production Capacity of Induction Furnace Product - Steel Billets From 29,988 Tpa to 2,10,000 Tpa, Rolling Mill Product - Narrow Strip /Rolled Products From 29,904 Tpa to 2,10,000 Tpa With Additional New Pipe Mill Product- Ms Pipe of Capacity 2,10,000 Tpa by M/S. Khayati Steel Industries PVT LTD is an approved industrial project in Nagenahalli, Tumakuru, Karnataka. The site covers 4.9 acres.

Who is building it?

The applicant is M/S Khayati Steel Industries PVT LTD..

Has it been approved?

Yes. Its status is “Environmental approval granted” (since 15 Sept 2023), as of 27 Nov 2026.

Where is it?

In Nagenahalli, Tumakuru, Karnataka.

How big is it?

It has a stated cost of ₹108.6 crore and a site of 4.9 acres.

When was it filed?

The application was filed on 15 Sept 2023.

Project details

StatusEnvironmental approval granted
Status since15 Sept 2023
Application filed15 Sept 2023
Approval soughtEnvironmental approval
Application typeExpansion
SectorIndustry
ApplicantM/S Khayati Steel Industries PVT LTD.
Land area4.9 acres (2 ha)
Project cost₹108.6 crore
Village / localityNagenahalli
Taluk / tehsilTumakuru
DistrictTumakuru
StateKarnataka
Location fromSite boundary on record
Our referenceWID-KA-00665

In context

14 applications in Tumakuru since January 2022 are in the same category (Industry): 11 approved, 2 filed or under review, and 1 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 4.9 acres, this one is larger than 50% of them.

10 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Nagenahalli, Tumakuru, Karnataka. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.