Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 2 Apr 2025 |
| Application filed | 27 Jan 2025 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Buildings & townships |
| Applicant | Vajram Estates Private Limited |
| Use | Residential |
| Units | 115 |
| Towers | 4 |
| Floors (tallest) | 4 |
| Basements | 1 |
| Parking spaces | 253 |
| Land area | 3.4 acres (1.4 ha) |
| Built-up area | 35,920 m² (3,86,639 sq ft) |
| Plot area | 13,555 m² (1,45,905 sq ft) |
| Project cost | ₹60 crore |
| Village / locality | Avalahalli |
| Taluk / tehsil | Yelahanka |
| District | Bangalore (Bengaluru) |
| State | Karnataka |
| Location from | Site boundary on record |
| Our reference | WID-KA-01465 |
What the filings say
What is planned
Vajram Estates Private Limited has proposed a residential apartment project at Avalahalli Village in Yelahanka, Bangalore. The project consists of four residential towers and a clubhouse. Each tower is designed with a configuration of a basement, ground floor, and four upper floors (B+G+4F). The total built-up area is 35,919.6 square metres, with a building height of 15.45 metres.
The development will provide 115 residential units. The floor-wise distribution of units is as follows:
- Ground Floor: 22 units
- First Floor: 22 units
- Second Floor: 23 units
- Third Floor: 24 units
- Fourth Floor: 24 units
Layout and design
The project is situated on a gross site area of 1.39 hectares (3.43 acres). After accounting for a kharab area of 303.47 square metres, the net residential site area is 13,554.86 square metres. The ground coverage accounts for 31.99% (4,337.44 square metres) of the site. Paved areas and driveways occupy 30.40%, while 37.61% (5,096.61 square metres) is dedicated to landscape and open spaces.
Parking facilities are planned in the basement and on the surface. While the requirement is for 152 car parking spaces, the applicant intends to provide 253 spaces, including 11 for visitors and 26 for the clubhouse.
Land and surroundings
The site is located at Survey No. 104 in Avalahalli. Several water bodies are located in the vicinity, including Singanayakanahalli Lake (560 metres northwest), Gantiganahalli Lake (1.47 km east), and Nagadasanahalli Lake (2.14 km north). The Avalahalli State Reserve Forest is approximately 1.61 km southwest of the project boundary. The site is situated about 0.7 km from State Highway 9 (Doddaballapura Road) and 5.88 km from National Highway 44.
Water, power and access
The total water requirement for the operational phase is estimated at 107 kilolitres per day (KLD). This includes a fresh water demand of 71 KLD, to be sourced from borewells or the Gram Panchayat, and 36 KLD of recycled water. Wastewater generation is expected to be 86 KLD, which will be treated in an on-site Sewage Treatment Plant (STP) with a capacity of 100 KLD using Sequencing Batch Reactor (SBR) technology. Treated water will be reused for flushing (36 KLD), landscaping (25 KLD), and maintenance activities.
Power will be sourced from the local grid with a transformer capacity of 750 KVA. A 250 KVA diesel generator (DG) set will be installed for backup. Energy-saving measures include solar water heaters, LED lighting for common areas, and solar-powered external lighting, aiming for total energy savings of approximately 21.46%.
Environmental safeguards
Solid waste generation is estimated at 370.35 kg per day. Biodegradable waste (223.9 kg/day) will be processed in an organic waste converter to be used as manure. Non-biodegradable waste (146.45 kg/day) will be handed over to authorised recyclers.
For rainwater harvesting, a roof rainwater sump with a capacity of 65 cubic metres is proposed. Five recharge pits (three for paved areas and two for hardscape) will be constructed to facilitate groundwater recharge. The landscape plan includes planting 170 trees of indigenous species such as Neem, Mango, and Chiku.
Timeline
The applicant's project report indicates a construction period of 36 months. During this phase, the water requirement of 11 KLD will be met through tertiary treated water from tankers, and a mobile STP will be used to treat 2.16 KLD of domestic wastewater generated by workers.
Vajram Estates Private Limited -Avalahalli site plan and layout
4 drawings from the project's filings. Sign in free to see them.
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see itIn context
1,390 applications in Bengaluru since January 2022 are in the same category (Buildings & townships): 1,004 approved, 205 filed or under review, and 178 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 3.4 acres, this one is smaller than 69% of them.
60 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Avalahalli, Yelahanka, Bengaluru, Karnataka. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Building project by Definer properties Pvt Ltd — more information requested, 600 m away
- Construction of Residential Development Namely CKPC Zenith — environmental approval granted, 700 m away
- Proposed Residential Apartment Building by Sri. Madhav R Badsheshi — environmental approval granted, 950 m away
- Proposed Modified Residential Apartment Building by Sri Madhav R Badsheshi — lapsed, 950 m away
- Modified Residential Apartment project by Sri Madhav R. Badsheshi, — lapsed, 950 m away
- Modified Residential Apartment project by Sri Madhav R. Badsheshi, — environmental approval granted, 950 m away
- Construction of Residential Apartment by M Gopala Reddy — initial checks, 1.1 km away
- Sattva Residential Development — initial checks, 1.2 km away
More from Vajram Estates Private Limited in Bangalore
- Building project by Vajram Estates Private Limited — environmental approval granted
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.