Quick answers
What is Sri Shrikant Anandrao Kadam?
Sri Shrikant Anandrao Kadam is an approved mining project in Hulikatti, Belagavi, Karnataka. The site covers 12 acres.
Who is building it?
The applicant is Shrikant Kadam.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 6 Aug 2024), as of 27 Nov 2026.
Where is it?
In Hulikatti, Belagavi, Karnataka.
How big is it?
It has a stated cost of ₹40 lakh and a site of 12 acres.
When was it filed?
The application was filed on 12 Apr 2024.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 6 Aug 2024 |
| Application filed | 12 Apr 2024 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Mining |
| Applicant | Shrikant Kadam |
| Land area | 12 acres (4.9 ha) |
| Project cost | ₹40 lakh |
| Village / locality | Hulikatti |
| Taluk / tehsil | Belagavi |
| District | Belagavi |
| State | Karnataka |
| Location from | Site boundary on record |
| Our reference | WID-KA-01476 |
In context
186 applications in Belagavi since January 2022 are in the same category (Mining): 137 approved, 26 filed or under review, and 23 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 12 acres, this one is larger than 91% of them.
3 other mining leases have applied within 500 m of this site; together with this one they cover 21.6 acres. Under India's environmental rules, mining leases less than 500 m apart are assessed together as one cluster, so the combined area can decide which clearance is needed. 21 mining leases have applied within 5 km.
Where it is
Hulikatti, Belagavi, Karnataka. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Environmental Clearance/Terms of Referance for Building Stone(M Sand) Quarry… — cleared for impact study, 0 m away
- Building Stone (M-Sand) Quarry (QL No. DMG/DD/BLGNS/1921/2025-26) "Sri.… — more information requested, 0 m away
- Mining project by M/S Om Stone Crusher Industries Sri Mahadev M Muchandi — environmental approval granted, 200 m away
- Mining project by M/S Om Stone Crusher Industries Sri Mahadev M Muchandi — cleared for impact study, 200 m away
- Shri Shrikant Anandrao Kadam — environmental approval granted, 250 m away
- Shri. Arun Ningappa Guruvannavar - Extent 4-20 Acre — withdrawn, 450 m away
- Environmental Clearance for Building Stone Quarry in 1-20 Acres of Patta Land… — environmental approval granted, 550 m away
- Mining project by M/S Aaditya Resources Sri Shegar Raghavan — environmental approval granted, 600 m away
More from Shrikant Kadam in Belagavi
- Shri Shrikant Anandrao Kadam — environmental approval granted
- Environmental Clearance/Terms of Referance for Building Stone(M Sand) Quarry… — cleared for impact study
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.