Quick answers
What is this project?
Proposed 10000 TCD Sugar, 400 KLPD Sugar juice/Syrup/Molasses based Distillery, 320 KLPD Grain Based Distillery and 32 MW Cogeneration Power plant at Survey.no 13,14,15 Village Hadnur, Tal. Jevargi Dist. Kalaburagi, Karnataka Proposed by Akshay Biofuels Pvt.Ltd is a proposed industrial project in Hadnur, Jevargi, Kalaburagi, Karnataka. The site covers 58 acres.
Who is building it?
The applicant is Akshay Bio Fuels Private limited.
Has it been approved?
Yes. Its status is “Cleared for impact study” (since 27 Apr 2026), as of 27 Nov 2026.
Where is it?
In Hadnur, Jevargi, Kalaburagi, Karnataka.
How big is it?
It has a stated cost of ₹550 crore and a site of 58 acres.
When was it filed?
The application was filed on 20 Nov 2024.
One of 3 filings for this project. The project's main page, with every filing and where each stands: Proposed 10000 TCD Sugar, 400 KLPD Sugar juice/Syrup/Molasses based Distillery, 320 KLPD…
Project details
| Status | Cleared for impact study |
|---|---|
| Status since | 27 Apr 2026 |
| Application filed | 20 Nov 2024 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Industry |
| Applicant | Akshay Bio Fuels Private limited |
| Land area | 58 acres (23.5 ha) |
| Project cost | ₹550 crore |
| Village / locality | Hadnur |
| Taluk / tehsil | Jevargi |
| District | Kalaburagi |
| State | Karnataka |
| Location from | Site boundary on record |
| Our reference | WID-KA-01732 |
All filings for this project
This project has 3 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 6 Mar 2026 | Environmental approval granted | 58 acres | ₹550 crore |
| New project filed 2 Dec 2025 | Returned to applicant | 58 acres | ₹550 crore |
| Early planning filed 20 Nov 2024 (this page) | Cleared for impact study | 58 acres | ₹550 crore |
In context
38 applications in Kalaburagi since January 2022 are in the same category (Industry): 23 approved, 9 filed or under review, and 6 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 58 acres, this one is smaller than 92% of them.
Where it is
Hadnur, Jevargi, Kalaburagi, Karnataka. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Proposed 10000 TCD Sugar, 400 KLPD Sugar juice/Syrup/Molasses based… — environmental approval granted, 0 m away
- Proposed 10000 TCD Sugar, 400 KLPD Sugar juice/Syrup/Molasses based… — returned to applicant, 0 m away
- 1000 Acre (404.69 Ha.) Prime Minister - Mega Integrated Textile Region and… — environmental approval granted, 9.9 km away
- 1000 Acre (404.69 Ha.) Prime Minister - Mega Integrated Textile Region and… — cleared for impact study, 9.9 km away
- Proposed Integrated Cement Plant - Clinker (4.0 Million TPA), Cement {6.66 (2… — lapsed, 10 km away
- Proposed Farhatabad Limestone Mine (ML Area: 1445.83 ha.) with Limestone… — lapsed, 10.2 km away
- Gulbarga Cement Limited: "Proposed Integrated Cement Plant having production… — environmental approval granted, 13.3 km away
- Gulbarga Cement Limited: "Proposed Integrated Cement Plant having production… — cleared for impact study, 13.3 km away
All 3 Akshay Bio Fuels projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.