| Official title | Expansion of existing Pig Iron and Foundry and establishment of new project at Bevinahalli Village & Post, Taluk & District Koppal, Karnataka by M/s. Kirloskar Ferrous Industries Limited |
|---|---|
| Status | Environmental approval granted |
| Status since | 21 Feb 2025 |
| Application filed | 20 Dec 2024 |
| Approval sought | Environmental approval |
| Application type | Expansion |
| Sector | Industry |
| Applicant | Kirloskar Ferrous Industries |
| Land area | 401.2 acres (162.4 ha) |
| Project cost | ₹3,403 crore |
| Village / locality | Kanakapura |
| Taluk / tehsil | Koppal |
| District | Koppal |
| State | Karnataka |
| Location from | Site area on record |
| Our reference | WID-KA-01752 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Expansion filed 20 Dec 2024 (this page) | Environmental approval granted | 401.2 acres | ₹3,403 crore |
| Early planning filed 7 Jul 2023 | Cleared for impact study | 401.2 acres | ₹3,403 crore |
In context
48 applications in Koppal since January 2022 are in the same category (Industry): 28 approved, 16 filed or under review, and 4 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 401.2 acres, this one is larger than 92% of them.
20 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Kanakapura, Koppal, Karnataka. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Expansion of existing Pig Iron and Foundry and establishment of new project by… — cleared for impact study, 150 m away
- Proposed Expansion of the Alloy Steel Rolling Facilities From 0.7 MTPA to 0.9… — cleared for impact study, 1.5 km away
- Proposed Expansion of the Alloy Steel Rolling Facilities From 0.7 MTPA to 0.9… — cleared for impact study, 1.7 km away
- Proposed Expansion of the Alloy Steel Rolling Facilities from 0.7 Million TPA… — cleared for impact study, 1.8 km away
- Expansion in Cement Production Capacity of Existing Stand-alone Grinding Unit… — initial checks, 2.2 km away
- Expansion in Cement Production capacity of Stand-alone Grinding Unit from 1.5… — cleared for impact study, 2.3 km away
- Expansion of Steel Plant of Mukand Limited (400000 Mtpa to 700000 Mtpa) — environmental approval granted, 2.4 km away
- Expansion of Integrated Steel Plant by increasing the production capacity of… — cleared for impact study, 3 km away
All 14 Kirloskar Ferrous Industries projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.