Quick answers
What is this project?
Amendment in Environmental Clearance Conditions issued to M/s.Godavari Biorefineries Limited is an approved industrial project in Handigund, Raybag, Belagavi, Karnataka. The site covers 382 acres.
Who is building it?
The applicant is Godavari Biorefineries LTD.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 16 Aug 2024), as of 27 Nov 2026.
Where is it?
In Handigund, Raybag, Belagavi, Karnataka.
How big is it?
It has a stated cost of ₹338.2 crore and a site of 382 acres.
When was it filed?
The application was filed on 30 Apr 2024.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 16 Aug 2024 |
| Application filed | 30 Apr 2024 |
| Approval sought | Environmental approval |
| Application type | Amendment |
| Sector | Industry |
| Applicant | Godavari Biorefineries LTD |
| Land area | 382 acres (154.6 ha) |
| Project cost | ₹338.2 crore |
| Village / locality | Handigund |
| Taluk / tehsil | Raybag |
| District | Belagavi |
| State | Karnataka |
| Location from | Site boundary on record |
| Our reference | WID-KA-01957 |
In context
63 applications in Belagavi since January 2022 are in the same category (Industry): 35 approved, 20 filed or under review, and 8 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 382 acres, this one is larger than 92% of them.
Where it is
Handigund, Raybag, Belagavi, Karnataka. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Dhawaleshwar Dolomite Quary of M/S Anand Minerals — environmental approval granted, 11.4 km away
- Diversion of forest land — more information requested, 19.1 km away
- PROPOSED 120 KLPD GRAIN BASED DISTILLERY (For fuel ethanol) by M/s.… — environmental approval granted, 19.6 km away
- Expansion of Sugarcane Crushing Unit from 4500 TCD to 12000 TCD, Co-generation… — environmental approval granted, 20.3 km away
- Expansion of Sugarcane Crushing Unit from 4500 TCD to 12000 TCD, Co-generation… — environmental approval granted, 20.3 km away
- Shri Mahalakshmi Stone Crusher, Prop : Shri Maruthi Chinnappa Waddar Sy no… — under environmental review, 20.8 km away
- Multi Village Water Supply Scheme to Birnal and Other 16 Villages (106… — more information requested, 21.3 km away
- THE TRANSMISSION SYSTEM FOR ESTABLISHING 400kV SUBSTATION AT MEKHALI — under forest review, 22.2 km away
All 4 Godavari Biorefineries projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.