Project details
| Status | Cleared for impact study |
|---|---|
| Status since | 3 Aug 2024 |
| Application filed | 20 May 2024 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Mining |
| Applicant | Lokya Naik Manthesh Naik |
| Land area | 3.2 acres (1.3 ha) |
| Project cost | ₹1.4 crore |
| Village / locality | Uchchangidurga |
| Taluk / tehsil | Harappanahalli |
| District | Vijayanagar |
| State | Karnataka |
| Location from | Site boundary on record |
| Our reference | WID-KA-02317 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 15 Nov 2025 | Environmental approval granted | 3.2 acres | ₹1.4 crore |
| Early planning filed 20 May 2024 (this page) | Cleared for impact study | 3.2 acres | ₹1.4 crore |
In context
167 applications in Vijayanagar since January 2022 are in the same category (Mining): 81 approved, 30 filed or under review, and 56 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 3.2 acres, this one is smaller than 61% of them.
4 other mining leases have applied within 500 m of this site; together with this one they cover 57.1 acres. Under India's environmental rules, mining leases less than 500 m apart are assessed together as one cluster, so the combined area can decide which clearance is needed. 42 mining leases have applied within 5 km.
Where it is
Uchchangidurga, Harappanahalli, Vijayanagar, Karnataka. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- "Building Stone Quarry" of M/S Sri Tulajabhavani Stone Crusher. — environmental approval granted, 0 m away
- Expansion of Building Stone Quarry (QL No. HPT-559/2020-21) "Sri. S.… — lapsed, 300 m away
- Exopansion of Environmental Clearance for Building Stone Quarry "Sri. S.… — lapsed, 300 m away
- For grant of M-Sand Quarry Lease & Approach Road in Sy.No.1/D & 1/A of… — lapsed, 450 m away
- For grant of M-Sand Quarry Lease & Approach Road in Sy.No.1/D & 1/A of… — not approved, 450 m away
- Building Stone Quarry — environmental approval granted, 700 m away
- Building Stone Quarry — cleared for impact study, 700 m away
- Building Stone quarry Sri. Srinivasa Basapathi for Quarry lease number HPT 569. — lapsed, 700 m away
More from Lokya Naik Manthesh Naik in Vijayanagar
- " Ucchangidurga Building Stone Quarry" of M/s. Tulaja Bhavani Stone Crusher — environmental approval granted