One of 2 filings for this project. The project's main page, with every filing and where each stands: 120 KLPD Multi Grain Based Biofuels/Distillery plant to produce 120 KLPD Rectified…
Project details
| Official title | Proposed Establishment of 120 KLPD Multi Grain Based Biofuels/Distillery plant to produce 120 KLPD Rectified Spirit/Extra Neutral Alcohol (ENA) /fuel ethanol plant and Captive Power Plant of 3 MW Capacity by M/s. S.R. Ballary Biofuels Private Limited., |
|---|---|
| Status | Cleared for impact study |
| Status since | 13 Mar 2024 |
| Application filed | 28 Feb 2024 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Industry |
| Applicant | S. R. Ballary Bio Fuels Private Limited |
| Land area | 14.3 acres (5.8 ha) |
| Project cost | ₹120.5 crore |
| Village / locality | Kerikoppa |
| Taluk / tehsil | Haveri |
| District | Haveri |
| State | Karnataka |
| Location from | Site area on record |
| Our reference | WID-KA-02716 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 8 Oct 2024 | Environmental approval granted | 14.3 acres | ₹120.5 crore |
| Early planning filed 28 Feb 2024 (this page) | Cleared for impact study | 14.3 acres | ₹120.5 crore |
In context
9 applications in Haveri since January 2022 are in the same category (Industry): 7 approved, 2 filed or under review, and 0 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval.
Where it is
Kerikoppa, Haveri, Karnataka. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- 120 KLPD Multi Grain Based Biofuels/Distillery plant to produce 120 KLPD… — environmental approval granted, 50 m away
- 200 KLPD GRAIN BASED ETHANOL PLANT AND 6 MW COGENERATION POWER PLANT Village… — environmental approval granted, 8.4 km away
- Diversion of forest land for approach Road to Negalur Tank, Haveri Taluk,… — lapsed, 12.4 km away
- "Ordinary Sand Block" Havanur Block No.02 of Sri. Siddappa Bhajanthri — lapsed, 12.5 km away
- Diversion of Forest land for the construction of a Sewage Treatment Plant in… — not approved, 13.4 km away
- Diversion of Forest Land for construction of Municipal Solid Waste Segregation… — under forest review, 13.7 km away
- Ordinary Sand Mining of Sri. Ramesh S Bhajantri — lapsed, 15.6 km away
- Chandapur Sand Block — environmental approval granted, 19.7 km away
About this information