Expansion of existing Sugarcane crushing Plant from 5000 TCD to 7500 TCD and existing Molasses based Distillery from 50 KLD to 110 KLD Multi feed (C - Molasses / B Heavy Molasses/ Cane Syrup/Cane Juice/Grain) Distillery Unit with 3.5 MW Power Plant by M/s. Sri Chamundeswari Sugars Limited is a proposed industrial project in Annur, Maddur, Mandya, Karnataka. The site covers 106 acres.
Who is building it?
The applicant is SRI CHAMUNDESWARI sUGARS LIMITED.
Has it been approved?
Yes. Its status is “Cleared for impact study” (since 24 Nov 2025), as of 27 Nov 2026.
Where is it?
In Annur, Maddur, Mandya, Karnataka.
How big is it?
It has a stated cost of ₹810.7 crore and a site of 106 acres.
When was it filed?
The application was filed on 22 Nov 2025.
Project details
| Status | Cleared for impact study |
|---|---|
| Status since | 24 Nov 2025 |
| Application filed | 22 Nov 2025 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Industry |
| Applicant | SRI CHAMUNDESWARI sUGARS LIMITED |
| Land area | 106 acres (42.9 ha) |
| Project cost | ₹810.7 crore |
| Village / locality | Annur |
| Taluk / tehsil | Maddur |
| District | Mandya |
| State | Karnataka |
| Location from | Site boundary on record |
| Our reference | WID-KA-03299 |
In context
5 applications in Mandya since January 2022 are in the same category (Industry): 2 approved, 3 filed or under review, and 0 withdrawn, lapsed or rejected.
Where it is
Annur, Maddur, Mandya, Karnataka. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Diversion of Forest land for Providing Multi Village Scheme to 51 Habitations — under forest review, 6.6 km away
- Forest land diversion for Improvement of Approach Road from Aretippur to… — lapsed, 9.8 km away
- Building Stone Quarry (QL No. 520, 521 and 435) "M/s. Malakamma KalluKutikara… — lapsed, 12.5 km away
- Building Stone Quarry (QL No. 969) "Smt. Padmamma" — lapsed, 12.6 km away
- Environmental Clearance for Building Stone Quarry in 2-00 Acres of Govt. Land… — environmental approval granted, 13.1 km away
- Building Stone Quarry — under environmental review, 13.4 km away
- Sri. B R Shivanna — initial checks, 13.5 km away
- Environmental Clearance for Building Stone Quarry in 1-00 Acres of Govt. Land… — environmental approval granted, 13.5 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.