What is Developing? Open the mapMap

Cleared for impact studyIndustry · Koppal, Karnataka

Environmental Clearance for Expansion of Sponge Iron (DRI) from 300 TPD to 800 TPD, Steel Billets from 90,000 TPA to 3,06,000 TPA, Induction Furnace for Steel making 25 T to 85 T, Ladle Refining 25 T, Captive Power Plant from 12 MW to 25 MW and Establishment of Rolling Mill for rolled products capacity 800 TPD, Reheating furnace with Coal gasifier 60 TPH PCI/PNG/FO, Slag Processing 150 TPD, Steel Scrap Processing 300 TPD, Land Extent from 95 Acres to 100.78 Acres (100 Acres 31 Guntas)

Environmental Clearance for Expansion of Sponge Iron (DRI) from 300 TPD to 800 TPD, Steel Billets from 90,000 TPA to 3,06,000 TPA, Induction Furnace for Steel making 25 T to 85 T, Ladle Refining 25 T, Captive Power Plant from 12 MW to 25 MW and Establishment of Rolling Mill for rolled products capacity 800 TPD, Reheating furnace with Coal gasifier 60 TPH PCI/PNG/FO, Slag Processing 150 TPD, Steel Scrap Processing 300 TPD, Land Extent from 95 Acres to 100.78 Acres (100 Acres 31 Guntas) is a proposed industrial project in Kunikeri, Koppal, Karnataka. The site covers 100.8 acres. Its stated project cost is ₹676 crore. As of 27 Nov 2026, its status is “Cleared for impact study” (since 21 Sept 2025).

See it on the live map All projects in Koppal

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Project details

StatusCleared for impact study
Status since21 Sept 2025
Application filed19 Sept 2025
Approval soughtEnvironmental approval
Application typeEarly planning
SectorIndustry
ApplicantIlc Iron & Steel Private Limited
Land area100.8 acres (40.8 ha)
Project cost₹676 crore
Village / localityKunikeri
Taluk / tehsilKoppal
DistrictKoppal
StateKarnataka
Location fromSite boundary on record
Our referenceWID-KA-03666

In context

48 applications in Koppal since January 2022 are in the same category (Industry): 28 approved, 16 filed or under review, and 4 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 100.8 acres, this one is larger than 58% of them.

35 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Kunikeri, Koppal, Karnataka. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.