Project details
| Official title | Establishment of Sponge Iron Plant (2 x 100 TPD) along with Captive Power Plant 8 MW (4 MW WHRB & 4 MW FBC) by M/s Kumaraswamy Ispat Pvt. Ltd. |
|---|---|
| Status | Environmental approval granted |
| Status since | 1 Jun 2026 |
| Application filed | 13 Apr 2026 |
| Approval sought | Environmental approval |
| Application type | Validity extension |
| Sector | Industry |
| Applicant | Kumara Swamy Ispat Private Limited |
| Land area | 17 acres (6.9 ha) |
| Project cost | ₹49.3 crore |
| Village / locality | Halakundi |
| Taluk / tehsil | Ballari |
| District | Ballari |
| State | Karnataka |
| Location from | Site boundary on record |
| Our reference | WID-KA-04373 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Validity extension filed 13 Apr 2026 (this page) | Environmental approval granted | 17 acres | ₹49.3 crore |
| Validity extension filed 7 Jun 2025 | Returned to applicant | 17 acres | ₹49.3 crore |
In context
80 applications in Ballari since January 2022 are in the same category (Industry): 45 approved, 15 filed or under review, and 20 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 17 acres, this one is smaller than 92% of them.
10 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Halakundi, Ballari, Karnataka. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Sponge Iron Plant (2 x 100 TPD) by M/s Kumaraswamy Ispat Pvt. Ltd — returned to applicant, 0 m away
- Sri. Chandrashekara Gowda.M S/o M.Siddaramana Gowda — environmental approval granted, 1.8 km away
- Quarrying of Murrum By Sri.Chandrashekar Gouda — environmental approval granted, 1.8 km away
- Splitting of E.C. granted to M/s. VRKP Sponge and Power Plant LLP. vide… — environmental approval granted, 2 km away
- Proposed Expansion of Sponge Iron Plant from 90,000 TPA to 4,40,000 TPA, Steel… — returned to applicant, 2 km away
- Expansion of Sponge Iron Plant from 150 TPD to 400 TPD by M/s. Supra Steel &… — environmental approval granted, 2.6 km away
- 2 X 100 TPD Sponge Iron (DRI) Plant and 2 MW Captive Power Generation Plant by… — environmental approval granted, 2.7 km away
- Expansion of DRI Kilns (Sponge Iron from 30,000 TPA to 90,000 TPA), New… — environmental approval granted, 2.9 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.