What is Developing? Open the mapMap

Under environmental reviewBuildings & townships · Bengaluru Rural, Karnataka

Embassy Millennium - Proposed Residential Development

Embassy Millennium - Proposed Residential Development is a proposed building project in Bodanahosahalli, Hosakote, Bengaluru Rural, Karnataka. The site covers 18.6 acres. Its stated project cost is ₹600 crore. As of 27 Nov 2026, its status is “Under environmental review” (since 17 Nov 2026).

See it on the live map All projects in Bengaluru Rural

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

One of 2 filings for this project. The project's main page, with every filing and where each stands: Embassy Millennium - Proposed Residential Development

Project details

StatusUnder environmental review
Status since17 Nov 2026
Application filed25 Aug 2026
Approval soughtEnvironmental approval
Application typeNew project
SectorBuildings & townships
ApplicantEmbassy Realty Ventures Limited
Land area18.6 acres (7.5 ha)
Project cost₹600 crore
Village / localityBodanahosahalli
Taluk / tehsilHosakote
DistrictBengaluru Rural
StateKarnataka
Location fromSite boundary on record
Our referenceWID-KA-04450

All filings for this project

This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):

FilingStatusLandCost
New project filed 25 Aug 2026 (this page)Under environmental review18.6 acres₹600 crore
Early planning filed 6 Apr 2026Cleared for impact study18.6 acres₹600 crore

What the filings say

What is planned

Embassy Realty Ventures Limited proposes to develop a residential project named "Embassy Millennium" on a plot area of 7.53 hectares (18.24 acres). The development is planned to include six residential towers and a clubhouse. Each tower will consist of three basements, a ground floor, and 45 upper floors, reaching a maximum height of 142.7 metres. The project is designed to accommodate 1,215 apartment units.

The total built-up area is 2,79,068.99 square metres. The applicant's project report specifies the following land use distribution:

Layout and design

The site is currently vacant land with a few dilapidated sheds and several trees, including coconut, eucalyptus, tamarind, mango, and a banyan tree. The banyan tree is slated for retention, while others will be removed. The site slopes from east to west with a contour level difference of 4 metres.

Parking is planned for 1,438 vehicles, meeting the local byelaw requirements. The project includes a 10-metre buffer for nalas (drains) crossing the site and a 12-metre buffer for the adjacent Bhodanahosahalli Lake. A foot track crossing the site will be retained in its current form.

Water, power and access

Water: During the operation phase, the total water requirement is estimated at 956 KLD. This will be sourced from borewells and roof rainwater. The net fresh water requirement is 632 KLD. The project will generate 860 KLD of sewage, which will be treated in two separate systems: a 570 KLD greywater treatment plant (using Ultra Filtration and Reverse Osmosis) and a 295 KLD blackwater treatment system (using an anaerobic digester and Sequential Batch Reactor). Treated water will be reused for flushing, landscaping, and domestic purposes.

Power: The total power requirement for operations is 7,402 kVA, to be sourced from the Bangalore Electricity Supply Company Limited (BESCOM). Emergency backup will be provided by six 750 kVA and one 250 kVA diesel generator (DG) sets.

Access: The site is located in front of National Highway 648 (Dobbaspet–Hosur). The nearest railway junction is Devangonthi, approximately 4.7 km away.

Environmental safeguards

The applicant proposes to plant 904 trees of 60 different native species to enhance biodiversity. For rainwater harvesting, the project includes a roof rainwater collection sump of 1,040 cubic metres, 21 recharge pits, and 4 recharge wells.

Solid waste generation is estimated at 3.3 metric tonnes per day. Biodegradable waste (2.1 MT/day) will be processed on-site using an Organic Waste Converter, while non-biodegradable waste (1.2 MT/day) will be sent to authorized recyclers. Hazardous waste, such as DG waste oil (2.08 KL/year), will be stored in leak-proof containers and disposed of through authorized recyclers.

Timeline

The baseline environmental study was conducted between March 2026 and May 2026. The applicant submitted the application for environmental clearance following the generation of standard Terms of Reference on 10 April 2026.

Embassy Millennium - Residential Development site plan and layout

4 drawings from the project's filings. Sign in free to see them.

Embassy Millennium - Residential Development: Site Plan: 6 towers, lake buffer, nala buffers, and STRR road reservation (preview)🔒 Sign in free to see it
Site Plan: 6 towers, lake buffer, nala buffers, and STRR road reservation
Embassy Millennium - Residential Development: Water Balance Chart: sourcing, treatment, and reuse of grey and black water (preview)🔒 Sign in free to see it
Water Balance Chart: sourcing, treatment, and reuse of grey and black water
Embassy Millennium - Residential Development: Topo map showing core project site and 10 km buffer area (preview)🔒 Sign in free to see it
Topo map showing core project site and 10 km buffer area
Embassy Millennium - Residential Development: Land sketch delineating the schedule property boundaries and adjacent lake (preview)🔒 Sign in free to see it
Land sketch delineating the schedule property boundaries and adjacent lake

In context

187 applications in Bengaluru Rural since January 2022 are in the same category (Buildings & townships): 138 approved, 29 filed or under review, and 20 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 18.6 acres, this one is larger than 60% of them.

31 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Bodanahosahalli, Hosakote, Bengaluru Rural, Karnataka. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

28 Embassy Group projects in Bangalore
All 32 Embassy Group projects across India

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.