What is this project?
Transfer of Environmental Clearance from SHRI HALASIDHANATH SAHAKARI SAKHAR KARKHANA LTD. to SHRI HALASIDHANATH CO-OPERATIVE SUGAR FACTORY LTD. located at Shankaranandnagar, Nipani, Dist.: Belgavi, Karnataka State is a lapsed industrial project in Kodni, Nippani, Belagavi, Karnataka. The site covers 103 acres.
Who is building it?
The applicant is Shri Halasidhanath Co Operative Sugar Factory Limited.
Has it been approved?
No. The application was lapsed on 21 Oct 2026, so it is no longer under consideration.
Where is it?
In Kodni, Nippani, Belagavi, Karnataka.
How big is it?
It has a stated cost of ₹368.9 crore and a site of 103 acres.
When was it filed?
The application was filed on 11 Aug 2026.
Project details
| Status | Lapsed |
|---|---|
| Status since | 21 Oct 2026 |
| Application filed | 11 Aug 2026 |
| Approval sought | Environmental approval |
| Application type | Ownership transfer |
| Sector | Industry |
| Applicant | Shri Halasidhanath Co Operative Sugar Factory Limited |
| Land area | 103 acres (41.7 ha) |
| Project cost | ₹368.9 crore |
| Village / locality | Kodni |
| Taluk / tehsil | Nippani |
| District | Belagavi |
| State | Karnataka |
| Location from | Site boundary on record |
| Our reference | WID-KA-04546 |
In context
63 applications in Belagavi since January 2022 are in the same category (Industry): 35 approved, 20 filed or under review, and 8 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 103 acres, this one is larger than 57% of them.
2 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Kodni, Nippani, Belagavi, Karnataka. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Kodni Ordinary Building Stone Quarry of Vilas L Gadiwaddar — environmental approval granted, 3.3 km away
- Environmental Clearance for Building Stone Quarry in 2-00 Acres of Govt.… — environmental approval granted, 3.4 km away
- For laying 110/33KV Transmission line from Shendur Village to Nippani Village… — more information requested, 8.8 km away
- Expansion of Industrial Building by M/s. SFS Group India Private Limited — environmental approval granted, 11.2 km away
- Common Bio-Medical Waste Treatment and Disposal Facility by M/s Banashankari… — environmental approval granted, 11.4 km away
- Common Bio-Medical Waste Treatment and Disposal Facility by M/s Banashankari… — cleared for impact study, 11.4 km away
- Common Bio-Medical Waste Treatment and Disposal Facility — cleared for impact study, 11.4 km away
- Establishment of Glass Products Manufacturing Unit — environmental approval granted, 11.6 km away