Quick answers
What is Building Stone Quarry "Smt. Pyarijan"?
Building Stone Quarry "Smt. Pyarijan" is a proposed mining project in Achapura, Sagar, Shivamogga, Karnataka. The site covers 2 acres.
Who is building it?
The applicant is Payrijan.
Has it been approved?
Not yet. The application is still under review: its status is “Under environmental review”, as of 27 Nov 2026.
Where is it?
In Achapura, Sagar, Shivamogga, Karnataka.
How big is it?
It has a stated cost of ₹40 lakh and a site of 2 acres.
When was it filed?
The application was filed on 21 Apr 2026.
Project details
| Status | Under environmental review |
|---|---|
| Status since | 9 Nov 2026 |
| Application filed | 21 Apr 2026 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Mining |
| Applicant | Payrijan |
| Land area | 2 acres (0.8 ha) |
| Project cost | ₹40 lakh |
| Village / locality | Achapura |
| Taluk / tehsil | Sagar |
| District | Shivamogga |
| State | Karnataka |
| Location from | Site boundary on record |
| Our reference | WID-KA-05312 |
In context
54 applications in Shivamogga since January 2022 are in the same category (Mining): 19 approved, 18 filed or under review, and 17 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 2 acres, this one is smaller than 61% of them.
No other mining lease on record has applied within 5 km of this site.
Where it is
Achapura, Sagar, Shivamogga, Karnataka. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- 110KV SC Line on DC Tower from existing 110KV Sagara-Shivamogga (SS1) line to… — lapsed, 4 km away
- Expansion of Environmental Clearance for Building Stone Quarry in 1-00 Acres… — environmental approval granted, 5.5 km away
- Diversion of 0.0186 Ha of Forest Land for the Construction of BTS Base… — initial checks, 8.8 km away
- Diversion of 0.0186 Ha of Forest Land for the Construction of BTS Base… — forest land use approved, 9 km away
- Diversion of 0.0186 Ha of Forest Land for the Construction of BTS Base… — forest land use approved, 9.2 km away
- Diversion of 0.0188 Ha of Forest Land for the Construction of BTS Base… — forest land use approved, 9.9 km away
- Wildlife Clearance for Widening of NH-69 to Four lane from Km 111.500 to Km… — application filed, 10.1 km away
- Widening of NH-69 to Four lane from Km 111.500 to Km 148.089 — under forest review, 10.1 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.