What is Mining project by M/s Goral Stone Crusher Sri Ramesh P Goral?
This proposed mining project by M/s Goral Stone Crusher Sri Ramesh P Goral is in Ganikop, Bailahongala, Belagavi, Karnataka. The site covers 1.9 acres.
Who is building it?
The applicant is Ramesh Parashram Goral.
Has it been approved?
Not yet. The application is still under review: its status is “Initial checks”, as of 27 Nov 2026.
Where is it?
In Ganikop, Bailahongala, Belagavi, Karnataka.
How big is it?
It has a stated cost of ₹25 lakh and a site of 1.9 acres.
When was it filed?
The application was filed on 1 Nov 2026.
Project details
| Status | Initial checks |
|---|---|
| Status since | 1 Nov 2026 |
| Application filed | 1 Nov 2026 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Mining |
| Applicant | Ramesh Parashram Goral |
| Land area | 1.9 acres (0.8 ha) |
| Project cost | ₹25 lakh |
| Village / locality | Ganikop |
| Taluk / tehsil | Bailahongala |
| District | Belagavi |
| State | Karnataka |
| Location from | Site boundary on record |
| Our reference | WID-KA-05720 |
In context
186 applications in Belagavi since January 2022 are in the same category (Mining): 137 approved, 26 filed or under review, and 23 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 1.9 acres, this one is smaller than 93% of them.
2 other mining leases have applied within 500 m of this site; together with this one they cover 9 acres. Under India's environmental rules, mining leases less than 500 m apart are assessed together as one cluster, so the combined area can decide which clearance is needed. 24 mining leases have applied within 5 km.
Where it is
Ganikop, Bailahongala, Belagavi, Karnataka. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Building Stone Quarry (QL No. 1886) "M/s. Basav Sand Works" — environmental approval granted, 400 m away
- Bulding Stone Quarry — environmental approval granted, 400 m away
- Mining project by M/s Pawan Metal Syndicates Sri Pawan B Udapudi — environmental approval granted, 700 m away
- Ganikoppa Building Stone (M-Sand) Quarry — environmental approval granted, 950 m away
- M/s Tarade Brothers Construction pvt ltd Sri Alam Tarde — environmental approval granted, 1.1 km away
- M/s Tarade Brothers Construction pvt ltd Sri Alam Tarde — environmental approval granted, 1.3 km away
- Sugarcane Crushing Plant of 5,000 TCD capacity, Co-gen power plant 25 MW and… — returned to applicant, 1.6 km away
- Mining project by M/S Aaditya Resources Sri Shegar Raghavan — environmental approval granted, 1.6 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.