One of 3 filings for this project. The project's main page, with every filing and where each stands: "Building Stone Quarry" of "Shri Manjunath M Battur".
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 12 Jun 2026 |
| Application filed | 23 Apr 2026 |
| Approval sought | Environmental approval |
| Application type | Ownership transfer |
| Sector | Mining |
| Applicant | Manjunath M Battur |
| Land area | 2 acres (0.8 ha) |
| Project cost | ₹1.2 crore |
| Village / locality | Sitalahari |
| Taluk / tehsil | Gadag |
| District | Gadag |
| State | Karnataka |
| Location from | Site boundary on record |
| Our reference | WID-KA-05762 |
All filings for this project
This project has 3 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Ownership transfer filed 23 Apr 2026 (this page) | Environmental approval granted | 2 acres | ₹1.2 crore |
| Ownership transfer filed 23 Apr 2026 | Environmental approval granted | 2 acres | ₹1.2 crore |
| Ownership transfer filed 23 Apr 2026 | Environmental approval granted | 2 acres | ₹1.2 crore |
In context
110 applications in Gadag since January 2022 are in the same category (Mining): 73 approved, 13 filed or under review, and 24 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 2 acres, this one is smaller than 86% of them.
3 other mining leases have applied within 500 m of this site; together with this one they cover 7 acres. Under India's environmental rules, mining leases less than 500 m apart are assessed together as one cluster, so the combined area can decide which clearance is needed. 16 mining leases have applied within 5 km.
Where it is
Sitalahari, Gadag, Karnataka. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Building Stone Quarry — environmental approval granted, 0 m away
- "Building Stone Quarry" of "Shri Manjunath M Battur" — environmental approval granted, 100 m away
- Building Stone Quarry" of Sri. NHV Rama Rao, — environmental approval granted, 100 m away
- "Building Stone Quarry" of "Shri Manjunath M Battur". — environmental approval granted, 200 m away
- Building Stone Quarry — environmental approval granted, 200 m away
- "Building Stone Quarry" of M/s Manjunath Stone Industries — lapsed, 300 m away
- Building Stone Quarry — lapsed, 350 m away
- Building Stone Quarry of Smt Seema M Bhasalagavi — under environmental review, 500 m away
About this information