Quick answers
What is this project?
Improvements to Road and Construction of Retaining Wall From 41.70 to 42.20 (Working Chainage 42.12 to 42.230 Km) in Thirthahalli Kundapura Road(Sh-52) is a proposed road project in Nidagodu, Hosanagara, Shivamogga, Karnataka. The site covers 3.6 acres.
Who is building it?
The applicant is Improvements to Road and Construction of Retaining wall from Ch: 41.70 to 42.20km in Thirthahalli-Kundapura Road (SH-52) in Hosanagara Taluk, Shimoga District.
Has it been approved?
Not yet. The application is still under review: its status is “More information requested”, as of 27 Nov 2026.
Where is it?
In Nidagodu, Hosanagara, Shivamogga, Karnataka.
How big is it?
It has a stated cost of ₹5.4 crore; a site of 3.6 acres and 1,190 m² of forest land.
When was it filed?
The application was filed on 25 Feb 2026.
Project details
| Official title | Improvements to Road and Construction of Retaining Wall From 41.70 to 42.20 (Working Chainage 42.12 to 42.230 Km) in Thirthahalli Kundapura Road(Sh-52) in Hosanagara Taluk Shivamogga District and Construction of Retaining Wall and Other Protection Works at Balebare Ghat in Thirthahalli Kundapura Road SH-52 Ch. 42.25 and 43.05 (Working Chainage 42.23 to 42.25 Km) in Hosanagara Taluk |
|---|---|
| Status | More information requested |
| Status since | 24 Nov 2026 |
| Application filed | 25 Feb 2026 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Roads & highways |
| Applicant | Improvements to Road and Construction of Retaining wall from Ch: 41.70 to 42.20km in Thirthahalli-Kundapura Road (SH-52) in Hosanagara Taluk, Shimoga District |
| Land area | 3.6 acres (1.5 ha) |
| Forest land | 1,190 m² |
| Project cost | ₹5.4 crore |
| Village / locality | Nidagodu |
| Taluk / tehsil | Hosanagara |
| District | Shivamogga |
| State | Karnataka |
| Location from | Site boundary on record |
| Our reference | WID-KA-06416 |
In context
11 applications in Shivamogga since January 2022 are in the same category (Roads & highways): 1 approved, 6 filed or under review, and 4 withdrawn, lapsed or rejected. At 3.6 acres, this one is smaller than 64% of them.
Where it is
Nidagodu, Hosanagara, Shivamogga, Karnataka. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Diversion of 0.0186 Ha of Forest Land for the Construction of BTS Base… — forest land use approved, 5.9 km away
- Multi-Village Water Supply Scheme to Nagara & other 1166 Habitations of… — more information requested, 6.3 km away
- Diversion of 0.0186 Ha of Forest Land for the Construction of BTS Base… — forest land use approved, 10.7 km away
- Re-diversion of 0.25 Ha of Forest Land for continuing the use of HW Microwave… — more information requested, 10.9 km away
- Re-diversion of 0.3 Ha of Forest Land for continuing the use of HW Microwave… — lapsed, 10.9 km away
- Diversion of forest land for the construction of 1X8 MVA 33/11 Kv Substation… — lapsed, 13.7 km away
- Diversion of 0.0186 Ha of Forest Land for the Construction of BTS Base… — lapsed, 14 km away
- BSNL 4G USO SATURATION PROJECT Nerlamane Village (Tenkabylu), Thirthahalli Tq — forest land use approved, 14.3 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.