Diversion of forest land in Belur, Hassan, Arsikere Taluks of Hassan District for laying of Underground Optical Fiber Cable Within the Right of Way (ROW) of road in favour of Dinesh Engineers Limited, Bengaluru is a proposed telecom project in Athigudda Kaval, Arsikere, Hassan, Karnataka. The site covers 11.7 acres.
Who is building it?
The applicant is Dinesh Engineers Limited.
Has it been approved?
Not yet. The application is still under review: its status is “Initial checks”, as of 27 Nov 2026.
Where is it?
In Athigudda Kaval, Arsikere, Hassan, Karnataka.
How big is it?
It has a stated cost of ₹60 lakh; a site of 11.7 acres and 1.8 acres (0.7 ha) of forest land.
When was it filed?
The application was filed on 7 Oct 2026.
Project details
| Status | Initial checks |
|---|---|
| Status since | 8 Oct 2026 |
| Application filed | 7 Oct 2026 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Telecom |
| Applicant | Dinesh Engineers Limited |
| Land area | 11.7 acres (4.8 ha) |
| Forest land | 1.8 acres (0.7 ha) |
| Project cost | ₹60 lakh |
| Village / locality | Athigudda Kaval |
| Taluk / tehsil | Arsikere |
| District | Hassan |
| State | Karnataka |
| Location from | Site boundary on record |
| Our reference | WID-KA-06656 |
In context
7 applications in Hassan since January 2022 are in the same category (Telecom): 5 approved, 1 filed or under review, and 1 withdrawn, lapsed or rejected. The approved ones took a median of 19 months from filing to approval.
Where it is
Athigudda Kaval, Arsikere, Hassan, Karnataka. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Rajanashiriyur Green Granite Quarry of Karnataka State Minerals Corporation… — lapsed, 9 km away
- Rajanshiriyur Green Granite Quarry — under environmental review, 9 km away
- Rajanshiriyur Green Granite Quarry — withdrawn, 9 km away
- Building Stone Quarry "Sri. B. K. Prabhakar" — more information requested, 11.5 km away
- Building Stone Quarry (QL No. HMG 458) "Sri. A.A. Madappa" — lapsed, 12.3 km away
- Shankarprasad Stone Crushing Industries LLP Forest Clearence Applied for… — lapsed, 12.4 km away
- Shankarprasad Stone Crushing Industries LLP Forest Clearence Applied for… — lapsed, 12.4 km away
- Building Stone Quarry(QL. No. HMG 557) "Sri. S. Vasantha Shekar" — environmental approval granted, 13.1 km away
All 31 Dinesh Engineers projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.