Quick answers
What is this project?
Diversion of Forest Land in Belagavi Forest Division for the Implementation of 45 Mld External Water Supply Scheme to the Proposed Industrial Node is a lapsed water and irrigation project in Kundargi, Gokak, Belagavi, Karnataka. The site covers 76.8 acres.
Who is building it?
The applicant is Karnataka Industrial Areas Development Board.
Has it been approved?
No. The application was lapsed on 7 Nov 2026, so it is no longer under consideration.
Where is it?
In Kundargi, Gokak, Belagavi, Karnataka.
How big is it?
It has a stated cost of ₹318 crore; a site of 76.8 acres and 2.3 acres (0.9 ha) of forest land.
When was it filed?
The application was filed on 23 Sept 2026.
Project details
| Official title | Diversion of Forest Land in Belagavi Forest Division for the Implementation of 45 Mld External Water Supply Scheme to the Proposed Industrial Node in Dharwad Taluk and District |
|---|---|
| Status | Lapsed |
| Status since | 7 Nov 2026 |
| Application filed | 23 Sept 2026 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Water & irrigation |
| Applicant | Karnataka Industrial Areas Development Board |
| Land area | 76.8 acres (31.1 ha) |
| Forest land | 2.3 acres (0.9 ha) |
| Project cost | ₹318 crore |
| Village / locality | Kundargi |
| Taluk / tehsil | Gokak |
| District | Belagavi |
| State | Karnataka |
| Location from | Site boundary on record |
| Our reference | WID-KA-06855 |
In context
20 applications in Belagavi since January 2022 are in the same category (Water & irrigation): 1 approved, 13 filed or under review, and 6 withdrawn, lapsed or rejected. At 76.8 acres, this one is smaller than 75% of them.
Where it is
Kundargi, Gokak, Belagavi, Karnataka. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Multi Village Water Supply Scheme to Degaon and other 16 Villages (29… — more information requested, 15.4 km away
- 45 KLPD Molasses (B & C Heavy)/ Cane Syrup based Distillery by Shri Someshwar… — environmental approval granted, 18.5 km away
- Application for Transfer of Lease for construction of Railway over bridge… — under forest review, 22.2 km away
- Forest Clearance Application for the Construction of Temporary Road for… — under forest review, 22.2 km away
- Expansion of Chemical Fertilizer & Chemical Manufacturing Plant at Sy. No.… — cleared for impact study, 22.4 km away
- Proposed for Establishment of 90 KLPD (Sugar Cane ]uice/Syrup/Molasses)… — under environmental review, 23.4 km away
- Estimate for Electrification of Koshekoppa-Nagaragali(Village) Hamlet through… — lapsed, 25.5 km away
- Diversion of Forest Land for the Upgradation and Development of Road From… — initial checks, 28.8 km away
More from Karnataka Industrial Areas Development Board in Belagavi
- Kanagala Industrial Area Phase - II over an area extent of 233.20 Ha (576.25… — under environmental review
- Kanagala Industrial Area Phase - II over an area extent of 233.20 Ha (576.25… — cleared for impact study
3 Karnataka Industrial Areas Development Board projects in Belagavi
All 109 Karnataka Industrial Areas Development Board projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.