Quick answers
What is Laying and Establishment of 11KV distribution line?
Laying and Establishment of 11KV distribution line is a proposed power project in Sulkeri, Beltangadi, Dakshina Kannada, Karnataka. The site covers 3.2 acres.
Who is building it?
The applicant is Mangalore Electricity Supply Company Limited.
Has it been approved?
Not yet. The application is still under review: its status is “More information requested”, as of 27 Nov 2026.
Where is it?
In Sulkeri, Beltangadi, Dakshina Kannada, Karnataka.
How big is it?
It has a stated cost of ₹78 lakh; a site of 3.2 acres and 1,120 m² of forest land.
When was it filed?
The application was filed on 20 Feb 2026.
One of 2 filings for this project. The project's main page, with every filing and where each stands: Laying and Establishment of 11KV distribution line
Project details
| Official title | Laying and Establishment of 11KV distribution line in Navara Village in Belthangady Taluk, Dakshina Kannada District for Electrification households of Kedelu ST Colony enclosure passing through Kudremuka wildlife division, Karkala in favour of Assistant Executive Engineer, Mangalore Electricity Company Limited (MESCOM), O & M. Sub Division Belthangady |
|---|---|
| Status | More information requested |
| Status since | 23 Nov 2026 |
| Application filed | 20 Feb 2026 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Power |
| Applicant | Mangalore Electricity Supply Company Limited |
| Land area | 3.2 acres (1.3 ha) |
| Forest land | 1,120 m² |
| Project cost | ₹78 lakh |
| Village / locality | Sulkeri |
| Taluk / tehsil | Beltangadi |
| District | Dakshina Kannada |
| State | Karnataka |
| Location from | Site boundary on record |
| Our reference | WID-KA-07189 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 20 Feb 2026 (this page) | More information requested | 3.2 acres | ₹78 lakh |
| New project filed 20 Jul 2025 | More information requested | 3.2 acres | ₹78 lakh |
In context
10 applications in Dakshina Kannada since January 2022 are in the same category (Power): 0 approved, 8 filed or under review, and 2 withdrawn, lapsed or rejected. At 3.2 acres, this one is smaller than 70% of them.
2 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Sulkeri, Beltangadi, Dakshina Kannada, Karnataka. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Laying and Establishment of 11KV distribution line — under wildlife review, 0 m away
- Laying and Establishment of 11KV distribution line — more information requested, 0 m away
- Laying and Establishment of 11KV distribution line — more information requested, 3 km away
- Laying and Establishment of 11KV distribution line — decision issued, 3 km away
- Laying and Establishment of 11KV distribution line — under wildlife review, 5.6 km away
- Laying and Establishment of 11KV distribution line — more information requested, 5.7 km away
- Laying and Establishment of 11KV distribution line — under wildlife review, 5.7 km away
- Laying and Establishment of 11KV distribution line — more information requested, 5.8 km away
More from Mangalore Electricity Supply Company Limited in Dakshina Kannada
- Laying and Establishment of 11KV distribution line — more information requested
- Laying and Establishment of 11KV distribution line — more information requested
- Laying and Establishment of 11KV distribution line — more information requested
- Laying and Establishment of 11KV distribution line — more information requested
- Laying and Establishment of 11KV distribution line — under wildlife review
- Laying and Establishment of 11KV distribution line — under wildlife review
15 Mangalore Electricity Supply projects in Dakshina Kannada
All 27 Mangalore Electricity Supply projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.