Quick answers
What is this project?
Providing New 11KV Linkline to for Arranging Uninterrupted Power Supply to Water Supply & Domestic Installation From 33KV Substation is a lapsed power project in Amte, Khanapur, Belagavi, Karnataka. The site covers 15.8 acres.
Who is building it?
The applicant is Hubli Eletricity Supply Company Limited.
Has it been approved?
No. The application was lapsed on 22 Apr 2024, so it is no longer under consideration.
Where is it?
In Amte, Khanapur, Belagavi, Karnataka.
How big is it?
It has a stated cost of ₹1 crore; a site of 15.8 acres and 1 acres (0.4 ha) of forest land.
When was it filed?
The application was filed on 3 Dec 2023.
Project details
| Status | Lapsed |
|---|---|
| Status since | 22 Apr 2024 |
| Application filed | 3 Dec 2023 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Power |
| Applicant | Hubli Eletricity Supply Company Limited |
| Land area | 15.8 acres (6.4 ha) |
| Forest land | 1 acres (0.4 ha) |
| Project cost | ₹1 crore |
| Village / locality | Amte |
| Taluk / tehsil | Khanapur |
| District | Belagavi |
| State | Karnataka |
| Location from | Site boundary on record |
| Our reference | WID-KA-07689 |
In context
10 applications in Belagavi since January 2022 are in the same category (Power): 0 approved, 6 filed or under review, and 4 withdrawn, lapsed or rejected. At 15.8 acres, this one is smaller than 80% of them.
8 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Amte, Khanapur, Belagavi, Karnataka. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Estimate for new 11KV power lInes to provide to Uninterruptrd Power Supply to… — lapsed, 2.2 km away
- M/s Shivashakti Minerals, Partner : Shri Shivaraj Maruti Basagunde Sy no 17… — environmental approval granted, 2.4 km away
- Sri Shankargowda Patil (Aluminous Laterite Quarry) Sy No 28,29,30 — environmental approval granted, 2.8 km away
- Diversion of forest land — more information requested, 3.2 km away
- Diversion of forest land — more information requested, 3.2 km away
- Providing Water Supply Scheme to Cobra School of Jungle Warfare and Tactics… — more information requested, 3.6 km away
- Upgradation to Two Lane with/without Paved Shoulder from Sanquelim to Belagavi… — lapsed, 4.4 km away
- Laterite Quarry "M/s. P.R. Minerals, Prop: Sri. Suraj Kedari More" — environmental approval granted, 4.6 km away
More from Hubli Eletricity Supply Company Limited in Belagavi
- Commissioning of 15kw Hybrid Off-Grid System With Battery Bank (12.5kw… — lapsed
- Estimate for Electrification of Koshekoppa-Nagaragali(Village) Hamlet through… — lapsed
- Estimate for new 11KV power lInes to provide to Uninterruptrd Power Supply to… — lapsed
All 4 Hubli Eletricity Supply projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.