| Status | Decision issued |
|---|---|
| Status since | 24 Oct 2024 |
| Application filed | 24 Oct 2024 |
| Approval sought | Wildlife review |
| Application type | New project |
| Sector | Power |
| Applicant | Jsw Renewable Energy (Vijayanagar) Limited. |
| Land area | 766.1 acres (310 ha) |
| Project cost | ₹4 lakh |
| Village / locality | Amaradevaragudda |
| Taluk / tehsil | Kudligi |
| District | Vijayanagar |
| State | Karnataka |
| Location from | Site boundary on record |
| Our reference | WID-KA-07926 |
In context
9 applications in Vijayanagar since January 2022 are in the same category (Power): 1 approved, 4 filed or under review, and 2 withdrawn, lapsed or rejected.
Where it is
Amaradevaragudda, Kudligi, Vijayanagar, Karnataka. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Diversion of Forest area for laying of Underground Optical Fibre Cable (OFC)… — lapsed, 7.7 km away
- Diversion of Forest area for laying of Underground Optical Fibre Cable (OFC)… — more information requested, 7.7 km away
- Diversion of Forest area for laying of Underground Optical Fibre Cable (OFC)… — lapsed, 7.7 km away
- Diversion of forest land in Somalapura Reserve Forest in respect of M/s MSPL… — forest land use approved, 10.3 km away
- Raising main, Gravity Main, Pump House, Substation, Transmission Line,… — more information requested, 11.9 km away
- Raising main, Gravity Main, Pump House, Substation, Transmission Line,… — decision issued, 11.9 km away
- Raising main, Gravity Main, Pump House, Substation, Transmission Line,… — forest land use approved, 12 km away
- 33 KV Interconnecting Transmission line for 600MW wind Power Project — more information requested, 12.2 km away
More from Jsw Renewable Energy (Vijayanagar) Limited. in Vijayanagar
- 33 KV Interconnecting Transmission line for 600MW wind Power Project — more information requested
All 6 Jsw Renewable Energy projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.