Quick answers
What is this project?
Expansion of existing rolling mill (TMT Bars from 1,01,500 TPA to 1,50,000 TPA) with inclusion of Steel Melt Shop (Billet production 1,18,500 TPA) by M/s. Gasha Steels Pvt. Ltd is a proposed industrial project in Pudusseri Central, Palakkad, Kerala. The site covers 6.4 acres.
Who is building it?
The applicant is Gasha Steels Private Limited.
Has it been approved?
Not yet. The application is still under review: its status is “Under environmental review”, as of 27 Nov 2026.
Where is it?
In Pudusseri Central, Palakkad, Kerala.
How big is it?
It has a stated cost of ₹47.5 crore and a site of 6.4 acres.
When was it filed?
The application was filed on 27 Feb 2025.
Project details
| Status | Under environmental review |
|---|---|
| Status since | 29 Jul 2026 |
| Application filed | 27 Feb 2025 |
| Approval sought | Environmental approval |
| Application type | Expansion |
| Sector | Industry |
| Applicant | Gasha Steels Private Limited |
| Land area | 6.4 acres (2.6 ha) |
| Project cost | ₹47.5 crore |
| Village / locality | Pudusseri Central |
| Taluk / tehsil | Palakkad |
| District | Palakkad |
| State | Kerala |
| Location from | Site boundary on record |
| Our reference | WID-KL-00839 |
In context
24 applications in Palakkad since January 2022 are in the same category (Industry): 10 approved, 8 filed or under review, and 6 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 6.4 acres, this one is larger than 57% of them.
27 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Pudusseri Central, Palakkad, Kerala. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Existing Mild Steel Re-Rolling mill by M/s. Gasha Steels (P) LTD — environmental approval granted, 50 m away
- Existing Mild Steel Re-Rolling mill by M/s. Gasha Steels (P) LTD — cleared for impact study, 50 m away
- Proposed Sanitary Landfill Development (Phase II) For Disposing The Inerts… — under environmental review, 150 m away
- Proposed Sanitary Landfill Development (Phase II) For Disposing The Inerts… — cleared for impact study, 150 m away
- Regularization of existing Mild Steel Re-Rolling mill by M/s. Lal Steels Pvt.… — lapsed, 550 m away
- Regularization of existing Mild Steel Re-Rolling mill by M/s. Lal Steels Pvt.… — more information requested, 550 m away
- Existing Re-Rolling mill by M/s. Prince TMT Steels Pvt Ltd — lapsed, 700 m away
- Existing Re-Rolling mill by M/s. Prince TMT Steels Pvt Ltd — more information requested, 700 m away
More from Gasha Steels Private Limited in Palakkad
- Existing Mild Steel Re-Rolling mill by M/s. Gasha Steels (P) LTD — environmental approval granted
- Existing Mild Steel Re-Rolling mill by M/s. Gasha Steels (P) LTD — cleared for impact study
All 3 Gasha Steels projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.