Quick answers
What is Construction of Mudh-Tsaga Road From Km 0.000 to Km 54.000?
Construction of Mudh-Tsaga Road From Km 0.000 to Km 54.000 is a proposed road project in Nyoma, Leh, Ladakh. The site covers 99.4 acres.
Who is building it?
The applicant is Ministry of Defense.
Has it been approved?
Not yet. The application is still under review: its status is “More information requested”, as of 27 Nov 2026.
Where is it?
In Nyoma, Leh, Ladakh.
How big is it?
It has a stated cost of ₹309.9 crore and a site of 99.4 acres.
When was it filed?
The application was filed on 10 Nov 2023.
Project details
| Status | More information requested |
|---|---|
| Status since | 10 Nov 2023 |
| Application filed | 10 Nov 2023 |
| Approval sought | Wildlife review |
| Application type | New project |
| Sector | Roads & highways |
| Applicant | Ministry of Defense |
| Land area | 99.4 acres (40.2 ha) |
| Project cost | ₹309.9 crore |
| Village / locality | Nyoma |
| Taluk / tehsil | Leh |
| District | Leh |
| State | Ladakh |
| Location from | Site boundary on record |
| Our reference | WID-LA-00039 |
In context
36 applications in Leh since January 2022 are in the same category (Roads & highways): 0 approved, 34 filed or under review, and 0 withdrawn, lapsed or rejected. At 99.4 acres, this one is larger than 71% of them.
Where it is
Nyoma, Leh, Ladakh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Rationalisation of Boundary of High Altitude Cold Desert (Changthang) Wildlife… — under wildlife review, 8.4 km away
- Rationalisation of Boundary of High Altitude Cold Desert (Changthang) Wildlife… — more information requested, 8.6 km away
- 4G Saturation Project Near Community Hall Tsaga — more information requested, 8.9 km away
- Training Node Area at Tara — more information requested, 10.4 km away
- Underground Cavern at Loma — more information requested, 11.7 km away
- Ug Cavern at Loma — more information requested, 11.7 km away
- 4G Saturation Project Mudh — more information requested, 11.8 km away
- 11 kV TRANSMISSION LINE ERECTION FROM NIDDER(NYOMA)- BRIGADE ARMY,… — under wildlife review, 13.1 km away
More from Ministry of Defense in Leh
- Diversion of 2.018 Ha of Wildlife Sanctuary land for Construction of road… — under wildlife review
- 403 Field Hospital at Hunder — more information requested
- Construction/Improvement of Road Loma-Hanle From Cl-9 to NH Double Lane… — more information requested
- Diversion of 41.462 Ha of Wlc Land for Construction of Road Chushul to Chushul… — under wildlife review
- Storage Facility at Km-148 (II) — under wildlife review
- Storage Facilities at Punguk — more information requested
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.