Quick answers
What is this project?
Proposed MCGM staff Quaretrs for SWM dept under Ashray Yojana cell (Under DCPR 33(3) (A) on plot bearing C.T.S. no. 1236, 1236/1, to 50 of Village Malad south in P/S ward,13.40 M, wide Ahimsa Marg, Malad west , Mumbai By MCGM is an approved building project in Greater Mumbai (M Corp.), Mumbai Suburban, Maharashtra. The site covers 1.8 acres.
Who is building it?
The applicant is Public Works Department.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 18 Nov 2022), as of 27 Nov 2026.
Where is it?
In Greater Mumbai (M Corp.), Mumbai Suburban, Maharashtra.
How big is it?
It has a stated cost of ₹170 crore and a site of 1.8 acres.
When was it filed?
The application was filed on 18 Nov 2022.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 18 Nov 2022 |
| Application filed | 18 Nov 2022 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Buildings & townships |
| Applicant | Public Works Department |
| Land area | 1.8 acres (0.7 ha) |
| Project cost | ₹170 crore |
| Village / locality | Greater Mumbai (M Corp.) |
| Taluk / tehsil | Mumbai Suburban |
| District | Mumbai Suburban |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-00646 |
What the filings say
What is planned
The Municipal Corporation of Greater Mumbai (MCGM) proposes to develop staff quarters for its Solid Waste Management (SWM) department under the Ashray Yojana cell. The project is planned on a 0.72-hectare (1.78-acre) plot in Malad West, Mumbai.
The applicant's project report specifies the construction of five residential buildings with varying heights and capacities:
- Building 1: Ground + 14 floors
- Building 2: Ground + 18 (partial) floors
- Building 3: Ground + 14 floors
- Building 4: Ground + 14 floors
- Building 5: Ground + 23 floors
The development is designed to provide a total of 817 tenements. The project also includes a fitness centre, society offices, and dedicated space for a sub-station and a Sewage Treatment Plant (STP).
Layout and design
The site is accessible via the 13.40-metre wide Ahimsa Marg. The layout includes internal access roads, including a 6.00-metre wide access road. The ground floor plans indicate entrance lobbies, meter rooms, and fire-fighting infrastructure.
Residential units are primarily designed as one-bedroom configurations, typically featuring a living/dining area, kitchen, bedroom, bathroom, and water closet (WC). The design incorporates refuge areas at specific levels, such as the 8th and 15th floors in taller blocks, to meet safety regulations.
| Item | Detail |
|---|---|
| Total Plot Area | 7,206.18 square metres |
| Proposed Built-up Area | 38,913.06 square metres |
| Permissible FSI | 4.00 |
| Total Tenements | 817 |
| Total Parking Provided | 106 spaces |
| STP Capacity | 450 KLD |
| Tallest Building | Ground + 23 floors |
Land and surroundings
The project site is located at Village Malad South in the P/S ward of Mumbai. It is bordered by residential developments such as Asmita Sand Dunes (G+20) and Devanshi CHS (G+10), as well as an existing garden. The applicant plans to develop a green belt and recreational ground (RG) area on-site, including the plantation of 90 trees and the use of Miyawaki forestation techniques.
Water, power and access
The total water requirement for the project is estimated at 469 Kilolitres per Day (KLD) during the non-monsoon season and 464 KLD during the monsoon season. The MCGM municipal supply will provide 309 KLD of fresh water.
Recycled water from the on-site STP will meet flushing (155 KLD) and landscaping (5 KLD) requirements. During the non-monsoon season, approximately 164 KLD of excess treated water will be generated, of which 4 KLD is intended for use in pavers and roadside plantation, with the remainder discharged to the municipal sewer.
Environmental safeguards
The applicant's Environmental Management Plan outlines several mitigation measures:
- Air Quality: Dust suppression using water sprays, covering construction material vehicles with tarpaulin, and wheel washing for vehicles.
- Noise: Installation of 6-metre high site barricading during construction and equipping Diesel Generator (DG) sets with acoustic enclosures to maintain sound levels within Central Pollution Control Board (CPCB) standards.
- Waste Management: An Organic Waste Converter (OWC) with a segregation area will be used to process biodegradable waste into manure.
- Water: A 450 KLD capacity STP will treat sewage, with treated water reused for flushing and landscaping to reduce fresh water demand.
MCGM Staff Quaretrs for SWM Dept Under Ashray Yojana Cell (Under DCPR 333 a site plan and layout
4 drawings from the project's filings. Sign in free to see them.
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see itIn context
1,858 applications in Mumbai Suburban since January 2022 are in the same category (Buildings & townships): 1,230 approved, 196 filed or under review, and 432 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 1.8 acres, this one is smaller than 52% of them.
587 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Greater Mumbai (M Corp.), Mumbai Suburban, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Close to Adani’s ₹7,514 Crore Dharavi Redevelopment: 47,076 Homes Planned in Major Mumbai Project (11.7 km away).
Other projects nearby
- Proposed SRA scheme on plot bearing CTS no 841, 842, 844, 847(pt) & 851 of… — lapsed, 250 m away
- Proposed SRA scheme on plot bearing CTS no 841, 842, 844, 847(pt) & 851 of… — lapsed, 250 m away
- Proposed Redevelopment on property bearing on C.T.S. No. 33/15 & 33/17,… — environmental approval granted, 250 m away
- Proposed Redevelopment on property bearing on C.T.S. No. 33/15 & 33/17,… — withdrawn, 250 m away
- Proposed Redevelopment on property bearing on C.T.S. No. 33/15 & 33/17,… — lapsed, 250 m away
- Expansion in Proposed Residential cum commercial building on plot bearing CTS… — environmental approval granted, 350 m away
- Expansion in Environmental clearance for Proposed Redevelopment of society… — environmental approval granted, 350 m away
- Proposed redevelopment of existing society building known as Sunder-Sangam… — not approved, 350 m away
More from Public Works Department in Mumbai Suburban
- Expansion of Existing Jetty, Fish landing jetty & Fish Drying Platform with… — recommended by coastal authority
- Fish Drying Platform with Stone Protection, Boat Repairing Area, Approach… — recommended by coastal authority
- Wharf-cum-Platform and Raising height of the Breakwater and Existing Jetty at… — recommended by coastal authority
- New Jetty and Widening of Existing Jetty with Stone Protection at Bhati… — recommended by coastal authority
- Jetty-Cum-Platform, Sloping Ramps, and Extension of the Existing Jetty at Madh… — recommended by coastal authority
- Sloping jetty at Mahul, Mumbai Suburban, Maharashtra — recommended by coastal authority
34 Public Works Department, Maharashtra projects in Mumbai
All 155 Public Works Department, Maharashtra projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.