What is Developing? Open the mapMap

Cleared for impact studyIndustry · Osmanabad, Maharashtra

Environment Clearance for Proposed Expansion of existing 4000 TCD Sugar Unit to 10000 TCD capacity and Establishment of 500 KLPD Sugarcane Syrup /"C"/"B" Heavy Molasses based Distillery, 100 KLPD Grain Based Distillery

Environment Clearance for Proposed Expansion of existing 4000 TCD Sugar Unit to 10000 TCD capacity and Establishment of 500 KLPD Sugarcane Syrup /"C"/"B" Heavy Molasses based Distillery, 100 KLPD Grain Based Distillery is a proposed industrial project in Ida, Bhum, Osmanabad, Maharashtra. The site covers 146 acres. Its stated project cost is ₹714.6 crore. As of 27 Nov 2026, its status is “Cleared for impact study” (since 23 Nov 2023).

See it on the live map All projects in Osmanabad

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

One of 2 filings for this project. The project's main page, with every filing and where each stands: Environment Clearance for Proposed Expansion of existing 4000 TCD Sugar Unit to 10000…

Project details

Official titleEnvironment Clearance for Proposed Expansion of existing 4000 TCD Sugar Unit to 10000 TCD capacity and Establishment of 500 KLPD Sugarcane Syrup /"C"/"B" Heavy Molasses based Distillery, 100 KLPD Grain Based Distillery along with 40 MW Co-generation Power Plant by AAYAN MULTITRADE LLP (Operative of Banganga SSK Ltd.)
StatusCleared for impact study
Status since23 Nov 2023
Application filed23 Nov 2023
Approval soughtEnvironmental approval
Application typeEarly planning
SectorIndustry
ApplicantAayan Multitrade LLP
Land area146 acres (59.1 ha)
Project cost₹714.6 crore
Village / localityIda
Taluk / tehsilBhum
DistrictOsmanabad
StateMaharashtra
Location fromSite boundary on record
Our referenceWID-MH-00815

All filings for this project

This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):

FilingStatusLandCost
Early planning filed 23 Nov 2023 (this page)Cleared for impact study146 acres₹714.6 crore
Expansion filed 23 Aug 2023Environmental approval granted146 acres₹714.6 crore

In context

19 applications in Osmanabad since January 2022 are in the same category (Industry): 13 approved, 2 filed or under review, and 4 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 146 acres, this one is larger than 84% of them.

1 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Ida, Bhum, Osmanabad, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

More from Aayan Multitrade LLP in Osmanabad

3 Aayan Multitrade projects in Osmanabad
All 4 Aayan Multitrade projects across India

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.