What is this project?
110 KLPD Molasses (B & C Heavy)/ Cane juice/ Grain based Distillery with 1.5 MW Captive Power Plant (CPP) by Yogeshwari Sugar Industries Pvt. Ltd., At: Laxminagar, Village: Limba, Tal.: Pathri, Dist.: Parbhani, Maharashtra State is an approved industrial project in Limba Tanda, Pathri, Parbhani, Maharashtra. The site covers 94.8 acres.
Who is building it?
The applicant is Yogeshwari Sugar Industries PVT LTD.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 8 Dec 2023), as of 27 Nov 2026.
Where is it?
In Limba Tanda, Pathri, Parbhani, Maharashtra.
How big is it?
It has a stated cost of ₹175 crore and a site of 94.8 acres.
When was it filed?
The application was filed on 21 Sept 2023.
Project details
| Official title | Establishment of 110 KLPD Molasses (B & C Heavy)/ Cane juice/ Grain based Distillery with 1.5 MW Captive Power Plant (CPP) by Yogeshwari Sugar Industries Pvt. Ltd., At: Laxminagar, Village: Limba, Tal.: Pathri, Dist.: Parbhani, Maharashtra State. |
|---|---|
| Status | Environmental approval granted |
| Status since | 8 Dec 2023 |
| Application filed | 21 Sept 2023 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Industry |
| Applicant | Yogeshwari Sugar Industries PVT LTD |
| Land area | 94.8 acres (38.4 ha) |
| Project cost | ₹175 crore |
| Village / locality | Limba Tanda |
| Taluk / tehsil | Pathri |
| District | Parbhani |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-02515 |
In context
12 applications in Parbhani since January 2022 are in the same category (Industry): 9 approved, 1 filed or under review, and 2 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 94.8 acres, this one is larger than 67% of them.
Where it is
Limba Tanda, Pathri, Parbhani, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Transfer of Environmental Clearance of Dakupimpri Sand Ghat, Parbhani from… — environmental approval granted, 5.1 km away
- Dakupimpri Sand Ghat, Parbhani — environmental approval granted, 5.1 km away
- Transfer of Environmental Clearance of Lasina Sand Ghat, Parbhani from Vandana… — environmental approval granted, 5.3 km away
- Lasina Sand Ghat, Parbhani — environmental approval granted, 5.3 km away
- Lasina Sand Spot — environmental approval granted, 6 km away
- Transfer of Environmental Clearance of Wangi Sand Ghat, Parbhani, from Vandana… — environmental approval granted, 8.3 km away
- Wangi Sand Ghat, Parbhani — environmental approval granted, 8.3 km away
- Thadipimpalgaon Sand Spot — environmental approval granted, 10.4 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.