What is this project?
Expansion of existing cane juice/syrup/molasses based distillery from 120 KLPD to 350 KLPD At Post: Warphal, Taluka: Partur, District: Jalna By M/s. Shraddha Energy & Infraprojects Private Limited is a lapsed industrial project in Warphal, Partur, Jalna, Maharashtra. The site covers 152.4 acres.
Who is building it?
The applicant is Shraddha Energy and Infraprojects Private Limited.
Has it been approved?
No. The application was lapsed on 29 Oct 2024, so it is no longer under consideration.
Where is it?
In Warphal, Partur, Jalna, Maharashtra.
How big is it?
It has a stated cost of ₹388.1 crore and a site of 152.4 acres.
When was it filed?
The application was filed on 20 Nov 2023.
Project details
| Status | Lapsed |
|---|---|
| Status since | 29 Oct 2024 |
| Application filed | 20 Nov 2023 |
| Approval sought | Environmental approval |
| Application type | Expansion |
| Sector | Industry |
| Applicant | Shraddha Energy and Infraprojects Private Limited |
| Land area | 152.4 acres (61.7 ha) |
| Project cost | ₹388.1 crore |
| Village / locality | Warphal |
| Taluk / tehsil | Partur |
| District | Jalna |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-02936 |
In context
36 applications in Jalna since January 2022 are in the same category (Industry): 26 approved, 4 filed or under review, and 6 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 152.4 acres, this one is larger than 94% of them.
3 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Warphal, Partur, Jalna, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Proposed Expansion of Sugar unit 4500 TCD to 10000 TCD and Cogeneration power… — environmental approval granted, 0 m away
- Proposed Expansion of Sugar unit 4500 TCD to 10000 TCD and Cogeneration power… — cleared for impact study, 0 m away
- Expansion of Existing Cane Juice/Syrup/Molasses based Distillery from 120 KLPD… — environmental approval granted, 0 m away
- Revalidation of prior EC of Sand Ghat Proposal of Nandra Sand Ghat Tq. Partur… — not approved, 9.4 km away
- Revalidation of prior EC of Sand Ghat Proposal of Nandra Sand Ghat Tq. Partur… — environmental approval granted, 9.4 km away
- Sand Ghat Proposal of Nandra Sand Ghat Tq. Partur Dist. Jalna Nearest Gut no… — environmental approval granted, 9.4 km away
- Revalidation of prior EC of Sand Ghat Proposal of Amba Sand Ghat Tq. Partur… — environmental approval granted, 11.4 km away
- Sand Ghat Proposal of Amba Sand Ghat Tq. Partur Dist. Jalna Nearest Gut no… — environmental approval granted, 11.4 km away
More from Shraddha Energy and Infraprojects Private Limited in Jalna
- Expansion of Existing Cane Juice/Syrup/Molasses based Distillery from 120 KLPD… — environmental approval granted
All 4 Shraddha Energy and projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.