Expansion of Dhuptala OC, for an increase in Production capacity from 1.70 MTPA to 2.50 MTPA in Land Area of 1070.49 ha

Expansion of Dhuptala OC, for an increase in Production capacity from 1.70 MTPA to 2.50 MTPA in Land Area of 1070.49 ha is a proposed mining project in Bhadangpuri, Rajura, Chandrapur, Maharashtra. The site covers 5,053.1 acres. Its stated project cost is ₹720.9 crore. As of 27 Nov 2026, its status is “Cleared for impact study” (since 30 Aug 2023).

See it on the live map All projects in Chandrapur

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Quick answers

What is this project?

Expansion of Dhuptala OC, for an increase in Production capacity from 1.70 MTPA to 2.50 MTPA in Land Area of 1070.49 ha is a proposed mining project in Bhadangpuri, Rajura, Chandrapur, Maharashtra. The site covers 5,053.1 acres.

Who is building it?

The applicant is Western Coalfields Limited.

Has it been approved?

Yes. Its status is “Cleared for impact study” (since 30 Aug 2023), as of 27 Nov 2026.

Where is it?

In Bhadangpuri, Rajura, Chandrapur, Maharashtra.

How big is it?

It has a stated cost of ₹720.9 crore and a site of 5,053.1 acres.

When was it filed?

The application was filed on 7 Jul 2023.

Project details

Official titleExpansion of Dhuptala OC, for an increase in Production capacity from 1.70 MTPA to 2.50 MTPA in Land Area of 1070.49 ha located in Sasti Village, Rajura Tehsil, Chandrapur Dist., Maharashtra under EIA, 2006.
StatusCleared for impact study
Status since30 Aug 2023
Application filed7 Jul 2023
Approval soughtEnvironmental approval
Application typeEarly planning
SectorMining
ApplicantWestern Coalfields Limited
Land area5,053.1 acres (2,044.9 ha)
Project cost₹720.9 crore
Village / localityBhadangpuri
Taluk / tehsilRajura
DistrictChandrapur
StateMaharashtra
Location fromSite boundary on record
Our referenceWID-MH-03111

All filings for this project

This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):

FilingStatusLandCost
Amendment filed 22 Nov 2023Returned to applicant5,053.1 acres₹720.9 crore
Early planning filed 7 Jul 2023 (this page)Cleared for impact study5,053.1 acres₹720.9 crore

In context

341 applications in Chandrapur since January 2022 are in the same category (Mining): 280 approved, 28 filed or under review, and 33 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 5,053.1 acres, this one is larger than 98% of them.

No other mining lease on record is within 500 m of this site; 4 have applied within 5 km.

Where it is

Bhadangpuri, Rajura, Chandrapur, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

More from Western Coalfields Limited in Chandrapur

42 Western Coalfields projects in Chandrapur
All 88 Western Coalfields projects across India

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.