Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 9 Apr 2025 |
| Application filed | 2 Sept 2024 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Buildings & townships |
| Applicant | Maharashtra Housing and Area Development Board |
| Use | Residential |
| Land area | 15.8 acres (6.4 ha) |
| Project cost | ₹132.2 crore |
| Village / locality | Nakshtrawadi |
| Taluk / tehsil | Aurangabad |
| District | Aurangabad |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-04349 |
What the filings say
What is planned
The Chhatrapati Sambhajinagar Housing & Area Development Board (MHADA) proposes an Economically Weaker Section (EWS) housing scheme under the Pradhan Mantri Awas Yojana (PMAY). The project is planned on a 6.4-hectare (15.81-acre) plot at Gat No. 9 in Nakshatrawadi, Aurangabad.
The development comprises 30 residential buildings, all with a configuration of Podium plus 7 floors (P+7), and one commercial building of P+5 floors. The project will provide a total of 1,770 flats, 72 shops, and 5 offices.
Building Configuration
| Building Name | Floors | Units | Height (m) |
|---|---|---|---|
| A1 to A4 | P+7 | 84 flats & 6 shops each | 23.95 |
| A5 to A12 | P+7 | 84 flats each | 23.35 |
| B1 | P+7 | 48 flats | 23.65 |
| B2 to B4 | P+7 | 42 flats each | 23.35 |
| B5 to B6 | P+7 | 42 flats & 6 shops each | 23.95 |
| B7 | P+7 | 42 flats | 23.35 |
| B8 to B13 | P+7 | 42 flats & 6 shops each | 23.95 |
| B14 to B18 | P+7 | 42 flats each | 23.35 |
| Commercial (D3) | P+5 | 5 offices | 21.05 |
Layout and design
The site layout is divided into Phase 1 and Phase 2. The project includes internal RCC roads of 9.0 metres width and is bordered by 15.0-metre wide draft Development Plan (DP) roads. The design incorporates open spaces, an amenity space of 2,552.42 square metres, and dedicated areas for a Sewage Treatment Plant (STP), an Organic Waste Converter (OWC), and transformers. Parking facilities are planned for 12 cars and 1,905 scooters.
Water, power and access
During the operation phase, the total water requirement is estimated at 1,261.72 kilolitres per day (KLD). Of this, 806.9 KLD will be fresh water sourced from the Chhatrapati Sambhajinagar Municipal Corporation (CSMC). The remaining 454.82 KLD for flushing and landscaping will be met through recycled water from the onsite STP.
Power will be supplied by the Maharashtra State Electricity Distribution Company Limited (MSEDCL), with a connected load of 5,517 kW and a maximum demand of 3,684 kW. Renewable energy through solar PV installations will contribute 184 kW. For emergency backup, two diesel generator (DG) sets of 125 kVA and 30 kVA capacities are proposed.
Environmental safeguards
Waste Management
The project will generate approximately 2,727 kg/day of wet garbage, which will be treated onsite using an Organic Waste Converter. Dry garbage (1,801 kg/day) will be handed over to the local body for recycling. A 1,200 KLD STP using Moving Bed Biofilm Reactor (MBBR) technology will treat domestic sewage. The resulting STP sludge (72 kg/day) is intended for use as manure in the project's green belt.
Rainwater Harvesting and Greenery
A rainwater harvesting system is planned with 30 recharge pits (8 for rooftop runoff and 22 for surface runoff). The total green belt area is 6,484.68 square metres, where 749 native trees will be planted.
Air and Noise
During construction, 15-foot high sheets will be used for site barricading to suppress dust and noise. Water sprinkling will be conducted for dust control. DG sets will be equipped with acoustic enclosures and stacks of 29 metres height to mitigate emissions and noise impacts.
Chatrapati Sambhajinagar Housing EWS Housing Scheme PMAY for MHADA site plan and layout
A drawing from the project's filings. Sign in free to see it.
🔒 Sign in free to see itIn context
91 applications in Aurangabad since January 2022 are in the same category (Buildings & townships): 52 approved, 18 filed or under review, and 21 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 15.8 acres, this one is larger than 52% of them.
5 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Nakshtrawadi, Aurangabad, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Aurangabad City Water Supply Project — in-principle approval, conditions pending, 1.1 km away
- Aurangabad City Water Supply Project — more information requested, 3.1 km away
- Proposed Expansion of Educational Campus & Ayurvedic Hospital Building at Gat… — under environmental review, 3.7 km away
- Proposed Educational Campus & Ayurvedic Hospital Building by M/s. Shreeyash… — environmental approval granted, 3.7 km away
- Proposed Residential & commercial project at Gat No. 62/1, 62/2, Itkheda… — environmental approval granted, 4.7 km away
- Proposed Multi speciality Centre by Marathwada Medical & Research Centre,… — not approved, 5.4 km away
- Proposed Multi-specialty Hospital by Marathwada Medical & Research Centre,… — lapsed, 5.4 km away
- Environmental Clearance for Proposed Residential and Commercial Project at CTS… — environmental approval granted, 5.9 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.