Quick answers
What is this project?
Environment Clearance for Proposed Slum Rehabilitation Scheme under Reg. 33 (10) of DCPR 2034 on plot bearing C.T.S. No. 5027 (pt.), 5063B, 5063B/7 to 17, 5045, 5046, 5065(pt.) of village, Kolekalyan, Santacruz East Mumbai for "Bharat SRA CHS (prop)" by M/s. Intercon Construction (I) Pvt. Ltd is an approved residential project in Greater Mumbai (M Corp.), Mumbai Suburban, Maharashtra. It plans 2 towers of up to 9 floors on 1.6 acres.
Who is building it?
The applicant is Intercon Constructions (I) PVT LTD.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 21 Jul 2025), as of 27 Nov 2026.
Where is it?
In Greater Mumbai (M Corp.), Mumbai Suburban, Maharashtra.
How big is it?
It has a stated cost of ₹148.8 crore and a site of 1.6 acres.
When was it filed?
The application was filed on 11 Nov 2024.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 21 Jul 2025 |
| Application filed | 11 Nov 2024 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Buildings & townships |
| Applicant | Intercon Constructions (I) PVT LTD |
| Use | Residential |
| Towers | 2 |
| Floors (tallest) | 9 |
| Basements | 2 |
| Height | 30 m |
| Land area | 1.6 acres (0.7 ha) |
| Built-up area | 41,716 m² (4,49,027 sq ft) |
| Project cost | ₹148.8 crore |
| Village / locality | Greater Mumbai (M Corp.) |
| Taluk / tehsil | Mumbai Suburban |
| District | Mumbai Suburban |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-04639 |
What the filings say
What is planned
Intercon Constructions (I) Pvt. Ltd. is proposing a Slum Rehabilitation Scheme (SRS) under Regulation 33(10) of the Development Control and Promotion Regulations (DCPR) 2034. The project is located at Kolekalyan, Santacruz East, Mumbai, on a plot spanning 0.66 hectares (1.63 acres).
The development involves the construction of residential and rehabilitation components. The applicant's environmental management plan indicates that the project will include a sewage treatment plant (STP) with a total capacity of 285 kilolitres per day (KLD) and an organic waste converter (OWC) with a dedicated segregation area to process biodegradable waste into manure.
Water, Power and Access
The project's water requirements vary slightly between seasons. According to the water balance reports, the total water requirement during the non-monsoon season is 290 KLD, while during the monsoon season, it is 286 KLD. The primary source of fresh water is the Municipal Corporation of Greater Mumbai (MCGM), which will supply 183 KLD for domestic use.
Recycled water from the on-site STP will be used to meet flushing and landscaping needs. In the non-monsoon season, 107 KLD of recycled water will be utilized (103 KLD for flushing and 4 KLD for landscaping). During the monsoon, landscaping requirements are eliminated, and 103 KLD of recycled water will be used for flushing. The system is designed to generate 258 KLD of sewage, which will be treated to produce 233 KLD of treated water. Excess treated water, amounting to 126 KLD in the non-monsoon and 130 KLD in the monsoon, will be discharged.
For power backup, Diesel Generator (DG) sets will be installed. These will be equipped with acoustic enclosures designed to maintain a maximum sound pressure level of 75 dB(A) at one meter, in accordance with Central Pollution Control Board standards.
Environmental Safeguards
The applicant has outlined several mitigation measures for the construction and operation phases:
- Air Quality: During construction, water spraying will be used for dust suppression. Site barricading, initially set at 3 metres, is planned to be increased to 10 metres following municipal guidelines. Smog machines will also be deployed for dust control. For the operation phase, the plan promotes Electric Vehicles (EV) and specific tree species to reduce suspended particulate matter.
- Waste Management: Construction debris will be collected and reused on-site where possible. For operations, an OWC will handle biodegradable waste.
- Greenery: The project includes a designated Recreation Ground (RG) area of 488.79 square metres on "mother earth." The applicant plans to plant 100 trees, primarily local species, with at least 80% of the plantation to be completed during the construction phase.
- Noise Control: Construction workers will be provided with personal protective equipment such as ear muffs and plugs. Heavy machinery will be fitted with silencers and noise shields where necessary.
- Water Protection: Toilets will be provided for construction labour, with sewage diverted to existing sewer lines. Silt traps and diversion ditches will be used to manage surface run-off during site development.
Intercon Construction Environment Clearance for Proposed Slum Rehabilitation Scheme Under Reg. 33 10 of DCPR 2034 site plan and layout
3 drawings from the project's filings. Sign in free to see them.
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see itIn context
1,858 applications in Mumbai Suburban since January 2022 are in the same category (Buildings & townships): 1,230 approved, 196 filed or under review, and 432 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 1.6 acres, this one is smaller than 55% of them.
450 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Greater Mumbai (M Corp.), Mumbai Suburban, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Close to Adani’s ₹7,514 Crore Dharavi Redevelopment: 47,076 Homes Planned in Major Mumbai Project (12 km away).
Other projects nearby
- Proposed redevelopment & amalgamation of S.R. Scheme of Yogiraj Ashram SRA CHS… — environmental approval granted, 100 m away
- ENVIRONMENT CLEARANCE FOR PROPOSED EXPANSION OF REDEVELOPMENT ON PLOT BEARING… — under environmental review, 200 m away
- Environment Clearance for proposed redevelopment – Mathuradas Colony on plot… — environmental approval granted, 200 m away
- Environment Clearance for proposed redevelopment – Mathuradas Colony on plot… — withdrawn, 200 m away
- Proposed redevelopment project under scheme DCPR Regulation 33(20)B at plot… — environmental approval granted, 350 m away
- Proposed redevelopment project under scheme DCPR Regulation 33(20)B at plot… — environmental approval granted, 350 m away
- Environment Clearance for Proposed Expansion of Residential cum commercial… — lapsed, 400 m away
- Environment Clearance for Proposed Residential building on plot bearing CTS… — environmental approval granted, 400 m away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.