Application for Amendment and Expansion in EC for Residential cum commercial project

Application for Amendment and Expansion in EC for Residential cum commercial project is an approved mixed-use project in Nilemore, Vasai, Palghar, Maharashtra. The site covers 100.4 acres. Its stated project cost is ₹1,864.2 crore. As of 27 Nov 2026, its status is “Environmental approval granted” (since 21 Jul 2025).

See it on the live map All projects in Palghar

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Project details

Official titleApplication for Amendment and Expansion in EC for Residential cum commercial project at village Nilemore, Tal: Vasai, Dist: Palghar, Maharashtra by Shri. Anil R Gupta (P.A. HOLDER).
StatusEnvironmental approval granted
Status since21 Jul 2025
Application filed24 Aug 2024
Approval soughtEnvironmental approval
Application typeExpansion
SectorBuildings & townships
ApplicantAnil R Gupta
UseMixed use
Land area100.4 acres (40.6 ha)
Built-up area14,04,983 m² (1,51,23,097 sq ft)
Plot area4,06,286 m² (43,73,222 sq ft)
Project cost₹1,864.2 crore
Village / localityNilemore
Taluk / tehsilVasai
DistrictPalghar
StateMaharashtra
Location fromSite boundary on record
Our referenceWID-MH-05166

All filings for this project

This project has 4 applications on record. Each is a separate step (an impact study, an approval, an expansion…):

FilingStatusLandCost
Expansion filed 24 Aug 2024 (this page)Environmental approval granted100.4 acres₹1,864.2 crore
Early planning filed 22 May 2024Cleared for impact study100.4 acres₹1,864.2 crore
Expansion filed 18 Mar 2023Environmental approval granted95.1 acres₹1,385 crore
Early planning filed 18 Mar 2023Cleared for impact study95.1 acres₹1,385 crore

In context

250 applications in Palghar since January 2022 are in the same category (Buildings & townships): 152 approved, 49 filed or under review, and 49 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 100.4 acres, this one is larger than 91% of them.

75 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Nilemore, Vasai, Palghar, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.