What is Developing? Open the mapMap

Cleared for impact studyIndustry · Pune, Maharashtra

Expansion of Distillery (45 KLPD to 700 KLPD) by new installation of 655 KLPD Multi-feedstock (Molasses/Sugar Syrup/Grain) based Distillery plant for production of RS/ENA/IA/Ethanol/Sustainable Aviation fuel, expansion of Sugar Mill (5000 TCD to 15000 TCD)

Expansion of Distillery (45 KLPD to 700 KLPD) by new installation of 655 KLPD Multi-feedstock (Molasses/Sugar Syrup/Grain) based Distillery plant for production of RS/ENA/IA/Ethanol/Sustainable Aviation fuel, expansion of Sugar Mill (5000 TCD to 15000 TCD) is a proposed industrial project in Patas, Daund, Pune, Maharashtra. The site covers 200.2 acres. Its stated project cost is ₹2,369.9 crore. As of 27 Nov 2026, its status is “Cleared for impact study” (since 3 May 2026).

See it on the live map All projects in Pune

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Project details

Official titleExpansion of Distillery (45 KLPD to 700 KLPD) by new installation of 655 KLPD Multi-feedstock (Molasses/Sugar Syrup/Grain) based Distillery plant for production of RS/ENA/IA/Ethanol/Sustainable Aviation fuel, expansion of Sugar Mill (5000 TCD to 15000 TCD) along with Co-Generation Power Plant (19.5 MW to 70 MW) & Compressed Biogas Plant (CBG 30 TPD) at Village Patas, Taluka Daund, District Pune, Maharashtra by M/s. Bhima Sahakari Sakhar Karkhana Ltd.
StatusCleared for impact study
Status since3 May 2026
Application filed11 Dec 2024
Approval soughtEnvironmental approval
Application typeEarly planning
SectorIndustry
ApplicantBhima Sahakari Sakhar Karkhana LTD
Land area200.2 acres (81 ha)
Project cost₹2,369.9 crore
Village / localityPatas
Taluk / tehsilDaund
DistrictPune
StateMaharashtra
Location fromSite boundary on record
Our referenceWID-MH-05367

All filings for this project

This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):

FilingStatusLandCost
Expansion filed 8 Sept 2025Lapsed200.2 acres₹2,369.9 crore
Early planning filed 11 Dec 2024 (this page)Cleared for impact study200.2 acres₹2,369.9 crore

In context

121 applications in Pune since January 2022 are in the same category (Industry): 81 approved, 22 filed or under review, and 18 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 200.2 acres, this one is larger than 94% of them.

15 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Patas, Daund, Pune, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

More from Bhima Sahakari Sakhar Karkhana LTD in Pune

3 Bhima Sahakari Sakhar projects in Pune
All 4 Bhima Sahakari Sakhar projects across India

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.