| Official title | Expansion of Cement production capacity of Standalone Grinding Unit from 0.9 MTPA to 6.0 MTPA (Expansion in existing Cement Mill from 0.9 to 3.0 Million TPA in phase - I and additional Cement Mill of 3.0 Million TPA in Phase - II) At Village-Parli Vaijnath, Tehsil-Parli, District-Beed, Maharashtra by M/s. UltraTech Cement Limited (Unit: Parli Cement Works)) |
|---|---|
| Status | Environmental approval granted |
| Status since | 22 Dec 2025 |
| Application filed | 27 Nov 2024 |
| Approval sought | Environmental approval |
| Application type | Expansion |
| Sector | Industry |
| Applicant | UltraTech Cement Limited |
| Land area | 61.2 acres (24.8 ha) |
| Project cost | ₹750.1 crore |
| Village / locality | Parli (Rural) |
| Taluk / tehsil | Parli |
| District | Bid |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-05390 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Expansion filed 27 Nov 2024 (this page) | Environmental approval granted | 61.2 acres | ₹750.1 crore |
| Early planning filed 10 Jul 2024 | Cleared for impact study | 61.2 acres | ₹750.1 crore |
In context
17 applications in Bid since January 2022 are in the same category (Industry): 10 approved, 6 filed or under review, and 1 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 61.2 acres, this one is smaller than 59% of them.
2 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Parli (Rural), Parli, Bid, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Expansion of Cement production capacity of Standalone Grinding Unit from 0.9… — cleared for impact study, 0 m away
- Transfer of Environmental Clearance letter no. J-11011/872/ 2007-IA-II (I),… — under environmental review, 0 m away
- Transfer of Environmental Clearance letter no. J-11011/872/ 2007-IA-II (I),… — withdrawn, 0 m away
- Re-Diversion of Forest Land for Laying Underground Optical Fiber Cable along… — lapsed, 10.8 km away
- Laying Underground Optical Fiber Cable along the road in RoW of NH-548B — lapsed, 10.8 km away
- Diversion of 4.5075 Ha. Reserved forest land Survey No. 8/1 (Old Survey No.… — lapsed, 19.6 km away
- Shri. Pradip Madhukar Thombare, Stone Quarry (M L Area 2.90 ha) Production… — environmental approval granted, 25.6 km away
- Transfer of Environmental Clearance of Telasmukh 2 Sand Ghat, Beed from DMO,… — environmental approval granted, 25.8 km away
More from UltraTech Cement Limited in Bid
- Transfer of Environmental Clearance letter no. J-11011/872/ 2007-IA-II (I),… — under environmental review
- Transfer of Environmental Clearance letter no. J-11011/872/ 2007-IA-II (I),… — withdrawn
4 UltraTech Cement projects in Bid
All 182 UltraTech Cement projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.