What is this project?
Amendment in Environmental Clearance of Coastal Berth for Development of Mechanized Dust Free Cement Handling System With Connected Conveying System Including Adequate Silo Capacity, Bulk Dispatch System, Packing and Loading System is an approved port and coastal project in Creek, Uran, Raigarh, Maharashtra. The site covers 22.2 acres.
Who is building it?
The applicant is Jawaharlal Nehru Port Authority.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 11 Sept 2025), as of 27 Nov 2026.
Where is it?
In Creek, Uran, Raigarh, Maharashtra.
How big is it?
It has a stated cost of ₹266.6 crore and a site of 22.2 acres.
When was it filed?
The application was filed on 26 Jun 2024.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 11 Sept 2025 |
| Application filed | 26 Jun 2024 |
| Approval sought | Environmental approval |
| Application type | Amendment |
| Sector | Ports & coast |
| Applicant | Jawaharlal Nehru Port Authority |
| Land area | 22.2 acres (9 ha) |
| Project cost | ₹266.6 crore |
| Village / locality | Creek |
| Taluk / tehsil | Uran |
| District | Raigarh |
| State | Maharashtra |
| Location from | Site area on record |
| Our reference | WID-MH-05538 |
All filings for this project
This project has 4 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Amendment filed 25 Aug 2026 | Under environmental review | 22.2 acres | ₹266.6 crore |
| Amendment filed 26 Jun 2024 (this page) | Environmental approval granted | 22.2 acres | ₹266.6 crore |
| Amendment filed 19 Feb 2024 | Lapsed | 22.2 acres | ₹266.6 crore |
| New project filed 7 Feb 2024 | Lapsed | 22.2 acres | ₹266.6 crore |
In context
54 applications in Raigarh since January 2022 are in the same category (Ports & coast): 25 approved, 13 filed or under review, and 16 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 22.2 acres, this one is smaller than 64% of them.
23 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Creek, Uran, Raigarh, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Amendment in Environmental Clearance of Coastal Berth for Development of… — under environmental review, 50 m away
- Amendment in Environmental Clearance of Coastal Berth for Development of… — lapsed, 50 m away
- Amendment in Environmental Clearance of Coastal Berth for Development of… — lapsed, 50 m away
- Entrance Gate Building at Landing Jetty and Development of Adjacent Area in… — coastal clearance granted, 300 m away
- Warehouse and Other Facilities for Upgradation, Equipping and Operation,… — lapsed, 1000 m away
- Warehouse and Other Facilities for Upgradation, Equipping and Operation,… — environmental approval granted, 1.1 km away
- Warehouse and Other Facilities for Upgradation, Equipping and Operation,… — coastal clearance granted, 1.1 km away
- Proposed Jetty Pipelines Connectivity portion between Shallow Water Berth… — lapsed, 1.1 km away
More from Jawaharlal Nehru Port Authority in Raigarh
- Warehouse and Other Facilities for Upgradation, Equipping and Operation,… — lapsed
- Warehouse and Other Facilities for Upgradation, Equipping and Operation,… — environmental approval granted
- Balance work of 4th Container Terminal & Marine Container Terminal at JNPT by… — environmental approval granted
- Entrance Gate Building at Landing Jetty and Development of Adjacent Area in… — coastal clearance granted
- Balance work of 4th Container Terminal & Marine Container Terminal at JNPT by… — lapsed
- Warehouse and Other Facilities for Upgradation, Equipping and Operation,… — coastal clearance granted
12 Jawaharlal Nehru Port Authority projects in Raigarh
All 31 Jawaharlal Nehru Port Authority projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.