Quick answers
What is Slum Rehabilitation (SR) Scheme?
Slum Rehabilitation (SR) Scheme is a withdrawn residential project in Greater Mumbai (M Corp.), Mumbai Suburban, Maharashtra. The site covers 5.9 acres.
Who is building it?
The applicant is Marathon Nextgen Realty Limited.
Has it been approved?
No. The application was withdrawn on 17 Jul 2024, so it is no longer under consideration.
Where is it?
In Greater Mumbai (M Corp.), Mumbai Suburban, Maharashtra.
How big is it?
It has a stated cost of ₹276.4 crore and a site of 5.9 acres.
When was it filed?
The application was filed on 12 Jun 2024.
Project details
| Official title | Slum Rehabilitation (SR) Scheme at village Bhandup, Bhandup (West), Taluka Kurla, Mumbai – 400078 |
|---|---|
| Status | Withdrawn |
| Status since | 17 Jul 2024 |
| Application filed | 12 Jun 2024 |
| Approval sought | Environmental approval |
| Application type | Expansion |
| Sector | Buildings & townships |
| Applicant | Marathon Nextgen Realty Limited |
| Use | Residential |
| Land area | 5.9 acres (2.4 ha) |
| Project cost | ₹276.4 crore |
| Village / locality | Greater Mumbai (M Corp.) |
| Taluk / tehsil | Mumbai Suburban |
| District | Mumbai Suburban |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-05833 |
What the filings say
What is planned
Marathon Nextgen Realty Limited is proposing an expansion of a Slum Rehabilitation (SR) Scheme in Bhandup (West). The project involves the redevelopment of existing slums, which are currently partly demolished. The applicant previously received an Environmental Clearance (EC) on 18 May 2023 and has completed part of the construction. The current proposal seeks an expansion due to an increase in plot area, permissible Floor Space Index (FSI), and the total number of buildings.
The project is divided into rehabilitation and sale components. The rehabilitation portion includes 796 flats and various community facilities, while the sale portion consists of 1,979 flats. The planned occupancy for the entire scheme is estimated at 12,008 persons.
Building Configuration
| Building | Configuration | Details |
|---|---|---|
| Rehabilitation Building 1 | Basement + Ground + 22 Floors | 796 Rehab flats, retail shops, 4 Balwadis, 4 Welfare centers, 4 Society offices, 3 Community halls, Library, Women Entrepreneurship center |
| Rehabilitation Buildings 2, 3 & 4 | Underground + Ground + 22 Floors | Service areas and residential units |
| Sale Building 1 (Wings A, B, C) | Basement + Ground + 22 Floors | 1,979 Sale flats (total for all sale buildings), retail shops, 8 Society offices, School |
| Sale Building 2 (Wings A, B, C) | Underground + Ground + 22 Floors | Residential units |
| Sale Buildings 3, 4 & 5 | Underground + Ground + 22 Floors | Residential units |
| Sale Building 6 (Wings A, B) | Underground + Ground + 22 Floors | Residential units |
| Club House/Fitness Centre | -- | Recreational facility |
Layout and design
The total plot area is 23,697.15 square metres. After deductions for road setbacks and a sports complex reservation (9,939.71 square metres), the net plot area is 13,757.44 square metres. The project includes a recreational ground area of 1,112 square metres on the ground level.
Parking provisions include 402 spaces for four-wheelers and 101 spaces for two-wheelers. The layout plan indicates the project will be accessed via several proposed roads, including a 36.60-metre wide Tansa Pipeline Road on the north-west and a 27.45-metre wide road on the south-east.
Land and surroundings
The site is located at Bhandup in the Kurla Taluka of Mumbai Suburban district. It is situated in a residential zone according to the Development Plan remarks from the Municipal Corporation of Greater Mumbai (MCGM). The surrounding area is primarily residential and slum-based, with the Bhandup Pipeline Railway Line Road located to the west.
Environmental sensitivity analysis notes that Sanjay Gandhi National Park is approximately 1.00 km away, and the Thane Creek Flamingo Sanctuary is 4.00 km away. The applicant states the site is not affected by the Eco-Sensitive Zone (ESZ) of these areas, nor is it within a Coastal Regulation Zone (CRZ) or mangrove swamp.
Water, power and access
The total water requirement during the operation phase is 1,013 kilolitres per day (KLD) for domestic purposes, sourced from the MCGM. Secondary water requirements of 519 KLD (513 KLD for flushing and 6 KLD for gardening) will be met through treated sewage. A Sewage Treatment Plant (STP) with a capacity of 1,490 kilolitres is planned to treat the estimated 1,324 KLD of sewage generated.
Power will be supplied by the Maharashtra State Electricity Distribution Company Limited (MSEDCL), with a connected load of 7,333 KW and a maximum demand of 2,952 KW. Ten diesel generator sets with a total capacity of 5,120 kVA are planned for emergency backup.
Environmental safeguards
Solid waste management plans include an Organic Waste Converter (OWC) to treat 2,040 kg/day of biodegradable garbage. Non-biodegradable waste (3,061 kg/day) will be sent to authorized recyclers. For rainwater harvesting, the applicant proposes two tanks with a total capacity of 75 KL and 13 recharge pits. Energy-saving measures, including solar energy use, are expected to reduce consumption by 1%.
Slum Rehabilitation (SR) Scheme site plan and layout
4 drawings from the project's filings. Sign in free to see them.
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see itIn context
1,858 applications in Mumbai Suburban since January 2022 are in the same category (Buildings & townships): 1,230 approved, 196 filed or under review, and 432 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 5.9 acres, this one is larger than 76% of them.
259 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Greater Mumbai (M Corp.), Mumbai Suburban, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Close to Adani’s ₹7,514 Crore Dharavi Redevelopment: 47,076 Homes Planned in Major Mumbai Project (2.4 km away).
Other projects nearby
- Slum Rehabilitation (SR) Scheme on plot bearing CTS No. 87/A (pt), 87/ C (pt),… — withdrawn, 0 m away
- Slum Rehabilitation (SR) Scheme on plot bearing CTS No. 87/A (pt), 87/ C (pt),… — withdrawn, 0 m away
- Slum Rehabilitation (SR) Scheme on plot bearing CTS No. 87/A (pt), 87/ C (pt),… — withdrawn, 0 m away
- Application for EC (along with Consent to Establish as per MoEF&CC… — environmental approval granted, 100 m away
- Proposed SRA scheme on plot bearing C.T.S No. 87/D(Pt) of Village: Bhandup… — environmental approval granted, 100 m away
- Proposed Amendment/Expansion in Residential cum Commercial Development at plot… — cleared for impact study, 450 m away
- Proposed Amendment/Expansion in Residential cum Commercial Development at plot… — cleared for impact study, 450 m away
- Proposed Amendment & Expansion in Residential cum Commercial Development at… — environmental approval granted, 450 m away
More from Marathon Nextgen Realty Limited in Mumbai Suburban
- Slum Rehabilitation (SR) Scheme on plot bearing CTS No. 87/A (pt), 87/ C (pt),… — withdrawn
- Slum Rehabilitation (SR) Scheme on plot bearing CTS No. 87/A (pt), 87/ C (pt),… — withdrawn
- Slum Rehabilitation (SR) Scheme on plot bearing CTS No. 87/A (pt), 87/ C (pt),… — withdrawn
- Proposed SRA scheme on plot bearing C.T.S No. 87/D(Pt) of Village: Bhandup… — environmental approval granted
All 5 Marathon Nextgen Realty projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.