Project details
| Status | Not approved |
|---|---|
| Status since | 24 Jul 2025 |
| Application filed | 1 Oct 2024 |
| Approval sought | Environmental approval |
| Application type | Expansion |
| Sector | Buildings & townships |
| Applicant | Krishna Constructions |
| Use | Residential |
| Land area | 1.3 acres (0.5 ha) |
| Project cost | ₹48 crore |
| Village / locality | Kharadi |
| Taluk / tehsil | Pune City |
| District | Pune |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-06128 |
All filings for this project
This project has 3 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Expansion filed 1 Oct 2024 (this page) | Not approved | 1.3 acres | ₹48 crore |
| Early planning filed 24 Sept 2024 | Cleared for impact study | 1.3 acres | ₹47.1 crore |
| Early planning filed 25 Aug 2023 | Cleared for impact study | 1.3 acres | ₹48 crore |
What the filings say
What is planned
Krishna Constructions proposes an expansion of the "Lotus Court" project in Kharadi, Pune. According to the applicant's environmental impact assessment report, the project involves a single building with a configuration of basement, ground floor, mezzanine, podium, and 15 upper floors. The building reaches a height of 55.95 metres.
The project is designed to accommodate 126 residential tenements and a commercial area of 1,414.80 square metres. The total built-up area is stated as 23,054.67 square metres, which includes 12,989.84 square metres of Floor Space Index (FSI) area and 10,064.83 square metres of non-FSI area. The applicant noted that while a previous Environmental Clearance was granted for a smaller built-up area, the construction completed on-site reached 23,054.67 square metres, necessitating this application for expansion.
| Item | Detail |
|---|---|
| Total Plot Area | 10,100 sqm |
| Net Plot Area | 8,265.15 sqm |
| Total Built-up Area | 23,054.67 sqm |
| Residential Tenements | 126 |
| Expected Residents | 630 |
| Commercial Area | 1,414.80 sqm |
| Total Parking Area | 2,138.61 sqm |
| Building Height | 55.95 m |
| Configuration | B + G + Mezz. + Podium + 15 floors |
Layout and design
The site plan indicates a 9.00-metre wide internal road and an 18.00-metre wide proposed Development Plan (DP) road. The layout includes several open spaces: Open Space 1 (508.78 square metres) and two podium-level open spaces (Open Space 2 and 3) each measuring 231.795 square metres. An amenity space of 1,458.56 square metres is also provided.
The ground floor is planned with 12 shops, a temporary sales office, and a project office. A 6.00-metre wide fire driveway surrounds the building. Refuge areas of 65.64 square metres each are designated on the 7th and 12th floors.
Water, power and access
The project's daily sewage generation is estimated at 97.30 kilolitres per day (KLD). The applicant proposes a Sewage Treatment Plant (STP) with a capacity of 100 KLD using Moving Bed Biofilm Reactor (MBBR) technology. Treated water will be reused for flushing and gardening.
Power will be supported by a transformer and a Diesel Generator (DG) set. Energy conservation measures include solar water heaters with a capacity of approximately 9,450 litres per day and solar photovoltaic generation of 5.14 KW. LED fixtures are proposed for common areas.
Environmental safeguards
For solid waste management, the project expects to generate 198 kg of wet waste per day, which will be treated in-situ using an Organic Waste Converter (OWC). Dry waste, estimated at 145 kg per day, will be handed over to authorized agencies.
Rainwater harvesting will be implemented using three recharge pits with bore wells for terrace and runoff water, equipped with online filtration and oil/grease chambers. The landscape plan includes the plantation of 145 trees, focusing on local species that provide shade or bear fruit. During construction, the applicant plans to use Ready Mix Concrete (RMC) and fly ash blocks to reduce dust and noise pollution.
Krishna Constructions Project "Lotus Court" at Kharadi, Pune site plan and layout
2 drawings from the project's filings. Sign in free to see them.
🔒 Sign in free to see it
🔒 Sign in free to see itIn context
3,029 applications in Pune since January 2022 are in the same category (Buildings & townships): 2,001 approved, 415 filed or under review, and 613 withdrawn, lapsed or rejected. The approved ones took a median of 5 months from filing to approval. At 1.3 acres, this one is smaller than 89% of them.
496 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Kharadi, Pune City, Pune, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Proposed Project "Lotus Court" at Kharadi, Pune by M/s. Krishna Constructions — cleared for impact study, 0 m away
- Project "Lotus Court" at Kharadi, Pune by M/s. Krishna Constructions — cleared for impact study, 0 m away
- "Residential & Commercial Project" by M/s SVBPL Homes Pvt.Ltd. — environmental approval granted, 250 m away
- "Residential & Commercial Project" by M/s SVBPL Homes Pvt.Ltd. — cleared for impact study, 250 m away
- Environmental Clearance for Construction at 32/3 + 31/1/3 + 31/1/57 Kharadi,… — more information requested, 400 m away
- Environment Clearance for Construction at 32/3 + 31/1/3 + 31/1/57 Kharadi,… — lapsed, 400 m away
- Proposed Residential Project "Palm Drive" situated at Sr. No. 10/2A/30,31,32 &… — lapsed, 450 m away
- Proposed Residential Project "Palm Drive" situated at Sr. No. 10/2A/30,31,32 &… — environmental approval granted, 450 m away
3 Krishna Constructions projects in Pune
All 4 Krishna Constructions projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.