Quick answers
What is this project?
Setting up 70KLPD Malt Distillery and Malt Spirit Maturation plant is an approved industrial project in Bamhani, Nagpur (Rural), Nagpur, Maharashtra. The site covers 89 acres.
Who is building it?
The applicant is Pernod Ricard India Private Limited.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 3 Nov 2025), as of 27 Nov 2026.
Where is it?
In Bamhani, Nagpur (Rural), Nagpur, Maharashtra.
How big is it?
It has a stated cost of ₹1,785 crore and a site of 89 acres.
When was it filed?
The application was filed on 23 May 2025.
One of 3 filings for this project. The project's main page, with every filing and where each stands: Setting up 70KLPD Malt Distillery and Malt Spirit Maturation plant
Project details
| Official title | Setting up 70KLPD Malt Distillery and Malt Spirit Maturation plant along with 6MW Cogeneration Power Plant |
|---|---|
| Status | Environmental approval granted |
| Status since | 3 Nov 2025 |
| Application filed | 23 May 2025 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Industry |
| Applicant | Pernod Ricard India Private Limited |
| Land area | 89 acres (36 ha) |
| Project cost | ₹1,785 crore |
| Village / locality | Bamhani |
| Taluk / tehsil | Nagpur (Rural) |
| District | Nagpur |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-07230 |
All filings for this project
This project has 3 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Amendment filed 15 Jan 2026 | Environmental approval granted | 89 acres | ₹1,785 crore |
| New project filed 23 May 2025 (this page) | Environmental approval granted | 89 acres | ₹1,785 crore |
| Early planning filed 6 Dec 2024 | Cleared for impact study | 89 acres | ₹1,785 crore |
In context
79 applications in Nagpur since January 2022 are in the same category (Industry): 51 approved, 13 filed or under review, and 15 withdrawn, lapsed or rejected. The approved ones took a median of 43 days from filing to approval. At 89 acres, this one is larger than 68% of them.
24 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Bamhani, Nagpur (Rural), Nagpur, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Setting up 70KLPD Malt Distillery and Malt Spirit Maturation plant — environmental approval granted, 0 m away
- Setting up 70KLPD Malt Distillery and Malt Spirit Maturation plant — cleared for impact study, 0 m away
- Fuel station by M/s. Baidyanath Bio Fuels Private Limited — initial checks, 650 m away
- Proposed Greenfield Project for PET Tirecord Manufacturing Plant having… — environmental approval granted, 1.8 km away
- Proposed Greenfield Project for PET Tirecord Manufacturing Plant having… — cleared for impact study, 1.8 km away
- Addl. Butibori I.A. Village Tarsi Survey No 148 — lapsed, 1.9 km away
- Expansion of existing Unit to produce Aluminum Ingots from 0.06 to 0.247 MTPA,… — cleared for impact study, 1.9 km away
- Industrial project by M/S Varron Autokast Limited — cleared for impact study, 1.9 km away
3 Pernod Ricard projects in Nagpur
All 6 Pernod Ricard projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.