Quick answers
What is this project?
Environmental Clearance for Basalt Stone Quarry Project (Area 1.00 ha) with production capacity 5,000 Brass/Annum by Shri. Mahadev Kondiram Pokale is a lapsed mining project in Dudhebavi, Phaltan, Satara, Maharashtra. The site covers 2.5 acres.
Who is building it?
The applicant is Mahadev Kondiram Pokale.
Has it been approved?
No. The application was lapsed on 1 Apr 2026, so it is no longer under consideration.
Where is it?
In Dudhebavi, Phaltan, Satara, Maharashtra.
How big is it?
It has a stated cost of ₹60 lakh and a site of 2.5 acres.
When was it filed?
The application was filed on 28 Nov 2025.
Project details
| Official title | Environmental Clearance for Basalt Stone Quarry Project (Area 1.00 ha) with production capacity 5,000 Brass/Annum at Gut No.875/1 (Part) Village- Dudhebavi, Taluka- Phaltan, District- Satara, Maharashtra by Shri. Mahadev Kondiram Pokale |
|---|---|
| Status | Lapsed |
| Status since | 1 Apr 2026 |
| Application filed | 28 Nov 2025 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Mining |
| Applicant | Mahadev Kondiram Pokale |
| Land area | 2.5 acres (1 ha) |
| Project cost | ₹60 lakh |
| Village / locality | Dudhebavi |
| Taluk / tehsil | Phaltan |
| District | Satara |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-08205 |
In context
127 applications in Satara since January 2022 are in the same category (Mining): 100 approved, 9 filed or under review, and 18 withdrawn, lapsed or rejected. The approved ones took a median of 6 months from filing to approval. At 2.5 acres, this one is smaller than 99% of them.
No other mining lease on record has applied within 5 km of this site.
Where it is
Dudhebavi, Phaltan, Satara, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Rehabilitation, Upgradation & Widning of Existing Highway to 2l/4l + Ps(Rigid… — in-principle approval, conditions pending, 1.8 km away
- Diversion of Forest Land for Approach Road and Under This Road One Side… — more information requested, 3.7 km away
- Shri. Vasant Manohar Dange- Basalt Stone Quarry over an area of 2.40Ha — environmental approval granted, 6.4 km away
- Transfer of Environmental Clearance of Existing Stone Quarry Project (Area… — not approved, 11.2 km away
- Amendment in Environmental Clearance for Greenfield Project of SSP - 300 MTPD,… — environmental approval granted, 11.3 km away
- Diversion of Forest Land for laying of Underground water pipeline for… — lapsed, 11.8 km away
- Diversion of Forest Land for Laying of Underground Water Pipeline for… — lapsed, 11.8 km away
- Diversion of Forest Land for Upgradation and Widening of Road Construction… — under forest review, 12.7 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.