Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 21 Jul 2025 |
| Application filed | 21 Apr 2025 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Buildings & townships |
| Applicant | Indus Co-Operative Housing Society Limited |
| Use | Mixed use |
| Land area | 3.2 acres (1.3 ha) |
| Built-up area | 76,541 m² (8,23,880 sq ft) |
| Project cost | ₹280 crore |
| Village / locality | Greater Mumbai (M Corp.) |
| Taluk / tehsil | Greater Mumbai |
| District | Mumbai |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-09138 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 21 Apr 2025 (this page) | Environmental approval granted | 3.2 acres | ₹280 crore |
| New project filed 11 Dec 2024 | Recommended by coastal authority | 3.2 acres | ₹280 crore |
What the filings say
What is planned
Indus Co-operative Housing Society Limited proposes a residential-cum-commercial development on a 1.3-hectare (3.21-acre) plot in Mumbai. The applicant's project report describes the construction of two primary buildings with varying heights and functions.
Building No. 1 is a residential structure divided into three wings (A, B, and C). Each wing is planned with a configuration of one basement, a ground floor, one additional floor, followed by three levels of podiums (2nd to 4th), a 5th podium top, and residential floors from the 6th to the 22nd level. The building height is specified at 74.80 metres, with Wing B reaching 77.85 metres at the changing room top level. This building includes retail shops on the ground level.
Building No. 2 is designated for rehabilitation and redevelopment (AH/R&R) to be handed over to the Brihanmumbai Municipal Corporation (BMC). It is planned as a single tower with one basement, a stilt/ground floor, and 14 upper floors, reaching a height of 44.90 metres.
| Item | Detail |
|---|---|
| Total Plot Area | 1.3 hectares (13,011.37 sq.m) |
| Building 1 Height | 74.80 metres (Wings A & C), 77.85 metres (Wing B) |
| Building 2 Height | 44.90 metres |
| Building 1 Floors | 1 Basement + G + 1 + 4 Podiums + 17 Residential Floors |
| Building 2 Floors | 1 Basement + Stilt/G + 14 Floors |
| STP Capacity | 100 KLD |
Layout and design
The layout plan indicates the project is situated adjacent to the 36.00-metre wide Sewri-Chembur Link Road. The site features a 9.00-metre wide internal driveway and multiple 6.00-metre wide access roads. Three distinct "Landscape Open Spaces" (LOS) are planned: LOS No. 1 (2,603.75 sq.m), LOS No. 2 (179.58 sq.m), and LOS No. 3 (231.69 sq.m). An additional amenity space of 779.05 sq.m is located at the southern corner of the plot. The design incorporates a podium line and a building line set back from the main road and a nearby nalla (drain).
Land and surroundings
The project site is located at C S No. 2/4, Salt Pan Division in the F/North ward of Mumbai. A portion of the plot, measuring 3,513.71 sq.m, is identified as a "Natural Area" under the Development Plan (DP) 2034. The site is bordered by a nalla on its northern and eastern sides, with a basement line and building line established to maintain distance from this water body.
Water, power and access
The applicant plans to meet water requirements through ground water and municipal supply. To reduce fresh water demand, a 100 KLD (kilolitres per day) Sewage Treatment Plant (STP) using Moving Bed Biofilm Reactor (MBBR) technology will be installed. Treated water is intended for landscaping, flushing, and cooling for Diesel Generator (DG) sets. Rainwater harvesting will be implemented through percolation wells and storm water collection. Power backup will be provided by DG sets equipped with acoustic enclosures and stacks extending above the tallest building height.
Environmental safeguards
The Environment Management Plan (EMP) outlines several mitigation measures:
- Air Quality: Use of water sprinklers for dust suppression during construction and maintaining a green belt with native species to act as a sink for pollutants.
- Noise Control: Restricting noisy construction activities to daytime and providing earplugs/muffs for workers in high-noise areas.
- Waste Management: Segregation of solid waste into biodegradable and non-biodegradable streams. Biodegradable waste will be treated on-site using an organic waste converter.
- Disaster Management: The plan identifies flooding, earthquakes (Seismic Zone III), and fire as primary risks. It proposes structural resilience per Indian Standard (IS) codes, basement waterproofing, and clearly marked emergency escape routes.
Indus Co-operative Housing Building & Construction of "Residential Cum Commercial" Project Proposed site plan and layout
A drawing from the project's filings. Sign in free to see it.
🔒 Sign in free to see itIn context
583 applications in Mumbai since January 2022 are in the same category (Buildings & townships): 446 approved, 58 filed or under review, and 79 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 3.2 acres, this one is larger than 58% of them.
141 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Greater Mumbai (M Corp.), Greater Mumbai, Mumbai, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Proposed Building & Construction of "Residential cum Commercial" project… — recommended by coastal authority, 0 m away
- Environmental Clearance for Proposed Medical College Building, existing Diet… — lapsed, 450 m away
- Proposed Redevelopment of Transit Camp With Transit, LIG, MIG and HIG Type… — under environmental review, 650 m away
- Proposed Redevelopment of Transit Camp With Transit, LIG, MIG and HIG Type… — under environmental review, 650 m away
- Residential and Commercial development at Block 'C', Wadala Truck Terminus,… — lapsed, 850 m away
- Expansion of Residential and Commercial development at Block 'C', Wadala Truck… — lapsed, 850 m away
- Expansion of Residential and Commercial development at Block 'C', Wadala Truck… — cleared for impact study, 850 m away
- Residential and Commercial development at Block 'C', Wadala Truck Terminus,… — cleared for impact study, 850 m away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.