Quick answers
What is this project?
Environmental Clearance for Stone Quarry Project (Area 4.45 Ha) (Private Land) with production capacity 30,000 Brass/Annum by Shri. Om Gajanan Thokal is an approved mining project in Satefal, Ner, Yavatmal, Maharashtra. The site covers 11 acres.
Who is building it?
The applicant is Om Gajanan Thokal.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 24 Oct 2025), as of 27 Nov 2026.
Where is it?
In Satefal, Ner, Yavatmal, Maharashtra.
How big is it?
It has a stated cost of ₹70 lakh and a site of 11 acres.
When was it filed?
The application was filed on 5 Jan 2025.
Project details
| Official title | Environmental Clearance for Stone Quarry Project (Area 4.45 Ha) (Private Land) with production capacity 30,000 Brass/Annum at Khasra No. 575/1 (Part) Village- Satefal, Taluka- Ner, District- Yavatmal, Maharashtra by Shri. Om Gajanan Thokal. |
|---|---|
| Status | Environmental approval granted |
| Status since | 24 Oct 2025 |
| Application filed | 5 Jan 2025 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Mining |
| Applicant | Om Gajanan Thokal |
| Land area | 11 acres (4.5 ha) |
| Project cost | ₹70 lakh |
| Village / locality | Satefal |
| Taluk / tehsil | Ner |
| District | Yavatmal |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-10279 |
In context
302 applications in Yavatmal since January 2022 are in the same category (Mining): 251 approved, 19 filed or under review, and 32 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 11 acres, this one is larger than 74% of them.
No other mining lease on record has applied within 5 km of this site.
Where it is
Satefal, Ner, Yavatmal, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- 6-MW Solar Plant MSKVY 2.0 at Nababpur (33/11 KV Ner Substation) — lapsed, 16.2 km away
- Ner Bye-Pass Road Tq Ner Dist Yavatmal — in-principle approval, conditions pending, 18.1 km away
- Stone quarry proposal of Mr. Gopal Omkarmal Mor ,Vill. Bagwadi, Tq Darwha… — environmental approval granted, 20.3 km away
- Proposed 100 KLPD Grain Based Distillery — environmental approval granted, 20.6 km away
- Stone quarry proposal of Mr. Ankit Suresh Gandhi ,Vill. Bagwadi, Tq Darwha… — environmental approval granted, 20.7 km away
- Minor Mineral (Stone & Murrum) Quarry Project Lease Area: 1.00 Ha, Survey/Gat… — environmental approval granted, 21 km away
- Stone Quarry proposal of Mrs. Rohini Snehal Bhakre Vill.-Kolura , Tq. Ner ,… — lapsed, 21.4 km away
- Stone Quarry Proposal of Mr. Rajveersingh Amrutpalsingh Kapoor ,Vill.… — environmental approval granted, 27.5 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.