Quick answers
What is Change in production capacity?
Change in production capacity is a proposed industrial project in Dhatav Tarf Astami, Roha, Raigarh, Maharashtra. The site covers 23.6 acres.
Who is building it?
The applicant is Excel Industries Limited.
Has it been approved?
Not yet. The application is still under review: its status is “Initial checks”, as of 27 Nov 2026.
Where is it?
In Dhatav Tarf Astami, Roha, Raigarh, Maharashtra.
How big is it?
It has a stated cost of ₹283 crore and a site of 23.6 acres.
When was it filed?
The application was filed on 30 Mar 2025.
One of 2 filings for this project. The project's main page, with every filing and where each stands: Change in Production Capacity
Project details
| Official title | Change in production capacity under the provision of No Increase in Pollution Load as per para 7(ii) (b) of EIA Notification 2006 and amendments thereon by Excel Industries Limited at Plot No. 112, 20/1, OS-2, MIDC Dhatav, Tal-Roha, Dist-Raigad. |
|---|---|
| Status | Initial checks |
| Status since | 30 Mar 2025 |
| Application filed | 30 Mar 2025 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Industry |
| Applicant | Excel Industries Limited |
| Land area | 23.6 acres (9.6 ha) |
| Project cost | ₹283 crore |
| Village / locality | Dhatav Tarf Astami |
| Taluk / tehsil | Roha |
| District | Raigarh |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-10324 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 18 Oct 2025 | Initial checks | 23.6 acres | ₹283 crore |
| New project filed 30 Mar 2025 (this page) | Initial checks | 23.6 acres | ₹283 crore |
In context
260 applications in Raigarh since January 2022 are in the same category (Industry): 152 approved, 67 filed or under review, and 41 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 23.6 acres, this one is larger than 81% of them.
33 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Dhatav Tarf Astami, Roha, Raigarh, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Change in Production Capacity — initial checks, 0 m away
- Amendment in Environmental Clearance for project "Expansion of Chemical… — environmental approval granted, 0 m away
- Industrial project by M/s. FDC Ltd. — lapsed, 250 m away
- Industrial project by M/s. FDC Ltd. — withdrawn, 250 m away
- Industrial project by M/s. FDC Ltd. — cleared for impact study, 250 m away
- Project by Unichem Laboratories Limited — initial checks, 350 m away
- Proposed Expansion of Manufacturing Capacity of the Synthetic Organic… — under environmental review, 400 m away
- Proposed Expansion of Manufacturing Capacity of the Synthetic Organic… — returned to applicant, 400 m away
More from Excel Industries Limited in Raigarh
- Amendment in Environmental Clearance for project "Expansion of Chemical… — environmental approval granted
3 Excel Industries projects in Raigarh
All 5 Excel Industries projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.