Environmental approval grantedIndustry · Sangli, Maharashtra

Environmental Clearance for Proposed Establishment of 80 KLPD Grain based Distillery, 10 KLPD Malt Spirit Distillery by M/s. Grand Western Distilleries Private Limited

Environmental Clearance for Proposed Establishment of 80 KLPD Grain based Distillery, 10 KLPD Malt Spirit Distillery by M/s. Grand Western Distilleries Private Limited is an approved industrial project in Shirala, Sangli, Maharashtra. The site covers 24.7 acres. Its stated project cost is ₹146.4 crore. As of 27 Nov 2026, its status is “Environmental approval granted” (since 20 Sept 2025).

See it on the live map All projects in Sangli

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Project details

Official titleEnvironmental Clearance for Proposed Establishment of 80 KLPD Grain based Distillery, 10 KLPD Malt Spirit Distillery along with IMFL and Country Liquor Bottling Unit to be located at Plot No. E-12/1, MIDC's Shirala Growth Center, Tal.: Shirala, Dist.: Sangli, State Maharashtra by M/s. Grand Western Distilleries Private Limited.
StatusEnvironmental approval granted
Status since20 Sept 2025
Application filed16 Jan 2025
Approval soughtEnvironmental approval
Application typeNew project
SectorIndustry
ApplicantGrand Western Distilleries Private Limited
Land area24.7 acres (10 ha)
Project cost₹146.4 crore
Village / localityShirala
Taluk / tehsilShirala
DistrictSangli
StateMaharashtra
Location fromSite area on record
Our referenceWID-MH-11053

All filings for this project

This project has 3 applications on record. Each is a separate step (an impact study, an approval, an expansion…):

FilingStatusLandCost
New project filed 16 Jan 2025 (this page)Environmental approval granted24.7 acres₹146.4 crore
Early planning filed 2 Aug 2024Cleared for impact study24.7 acres₹146.4 crore
Early planning filed 3 Jun 2024Withdrawn24.7 acres₹146.4 crore

In context

44 applications in Sangli since January 2022 are in the same category (Industry): 30 approved, 8 filed or under review, and 6 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 24.7 acres, this one is smaller than 59% of them.

9 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Shirala, Sangli, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

All 3 Grand Western Distilleries projects across India

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.