Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 8 Oct 2026 |
| Application filed | 6 Feb 2026 |
| Approval sought | Environmental approval |
| Application type | Expansion |
| Sector | Buildings & townships |
| Applicant | Data Center Holdings India LLP |
| Use | IT / offices |
| Land area | 15.4 acres (6.3 ha) |
| Built-up area | 2,19,993 m² (23,67,983 sq ft) |
| Plot area | 62,490 m² (6,72,636 sq ft) |
| Project cost | ₹2,776.4 crore |
| Village / locality | Arewali |
| Taluk / tehsil | Thane |
| District | Thane |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-12413 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Expansion filed 6 Feb 2026 (this page) | Environmental approval granted | 15.4 acres | ₹2,776.4 crore |
| Early planning filed 1 Dec 2025 | Cleared for impact study | 15.4 acres | ₹2,776.4 crore |
In context
1,540 applications in Thane since January 2022 are in the same category (Buildings & townships): 1,001 approved, 200 filed or under review, and 339 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 15.4 acres, this one is larger than 78% of them.
181 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Arewali, Thane, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Proposed Expansion of Existing Data center Park by Data Center Holdings India… — cleared for impact study, 0 m away
- Data Centre project at Plot No. 14/2, 15 & 37, TTC Industrial Area, MIDC,… — withdrawn, 300 m away
- Data Centre project at Plot No. 14/2, 15 & 37, TTC Industrial Area, MIDC,… — environmental approval granted, 300 m away
- Proposed Data Centre project at Plot No. 14/2, 15 & 37, TTC Industrial Area,… — environmental approval granted, 300 m away
- Proposed development at Plot No. 8A/1/2A/1 & Plot No. 8A/1/2B, TTC-MIDC… — environmental approval granted, 450 m away
- Proposed development at Plot No. 8A/1/2A/1 & Plot No. 8A/1/2B, TTC-MIDC… — cleared for impact study, 450 m away
- "Gold Craft" by Gramercy Trade Industries Private Limited at GEN-2/1/A/1, MIDC… — environmental approval granted, 550 m away
- "Gold Craft" by Gramercy Trade Industries Private Limited at GEN-2/1/A/1, MIDC… — cleared for impact study, 550 m away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.