What is this project?
Expansion of Sugar Factory from 7,500 TCD to 13,500 TCD & Distillery Unit from 150 KLPD to 220 KLPD by using C/B heavy Molasses/ Cane Juice/ Cane Syrup/ Grain is a proposed industrial project in Dhavarwadi, Karad, Satara, Maharashtra. The site covers 102.1 acres.
Who is building it?
The applicant is Jaywant Sugars Limited.
Has it been approved?
Yes. Its status is “Cleared for impact study” (since 18 Nov 2026), as of 27 Nov 2026.
Where is it?
In Dhavarwadi, Karad, Satara, Maharashtra.
How big is it?
It has a stated cost of ₹896.4 crore and a site of 102.1 acres.
When was it filed?
The application was filed on 9 Oct 2026.
Project details
| Official title | Expansion of Sugar Factory from 7,500 TCD to 13,500 TCD & Distillery Unit from 150 KLPD to 220 KLPD by using C/B heavy Molasses/ Cane Juice/ Cane Syrup/ Grain along with Power Generation from 1.9 MW to 4 MW by Jaywant Sugars Ltd. (JSL) located at Village: Dhawarwadi & Marali, Tal.: Karad, Dist.: Satara, Maharashtra State |
|---|---|
| Status | Cleared for impact study |
| Status since | 18 Nov 2026 |
| Application filed | 9 Oct 2026 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Industry |
| Applicant | Jaywant Sugars Limited |
| Land area | 102.1 acres (41.3 ha) |
| Project cost | ₹896.4 crore |
| Village / locality | Dhavarwadi |
| Taluk / tehsil | Karad |
| District | Satara |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-13364 |
In context
36 applications in Satara since January 2022 are in the same category (Industry): 23 approved, 10 filed or under review, and 3 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 102.1 acres, this one is larger than 78% of them.
8 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Dhavarwadi, Karad, Satara, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Close to Ashok Iron Works Plans a 1.25 MW Windmill in Satara, Maharashtra (10.2 km away).
Other projects nearby
- Expansion of Sugar Factory from 7,500 TCD to 13,500 TCD & Distillery Unit from… — cleared for impact study, 50 m away
- Transfer of Environmental Clearance granted by the name of Shri. Hanmant… — lapsed, 2.2 km away
- Diversion of Forest Land for Construction of Approach Road for Private… — more information requested, 2.2 km away
- Environmental Clearance for Basalt Stone Quarry of Shri. Devraj Babaso Patil… — environmental approval granted, 2.2 km away
- 45 KLPD Distillery Unit — environmental approval granted, 2.5 km away
- Environmental Clearance for the Basalt stone quarry of Sou. Jayashri… — environmental approval granted, 3.5 km away
- Environmental Clearance for the Basalt Stone quarry of Shri. Sunil Tukaram… — environmental approval granted, 4.1 km away
- Environmental Clearance for the Basalt Stone Quarry of Shri. Sarang Balasaheb… — environmental approval granted, 4.3 km away
More from Jaywant Sugars Limited in Satara
- Expansion of Sugar Factory from 7,500 TCD to 13,500 TCD & Distillery Unit from… — cleared for impact study
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.