Quick answers
What is Aug. to to Nhava Sheva Water Supply Scheme , State III?
Aug. to to Nhava Sheva Water Supply Scheme , State III is a lapsed water and irrigation project in Warad, Khalapur, Raigarh, Maharashtra. The site covers 0.5 acres.
Who is building it?
The applicant is Maharashtra Jeevan Pradhikaran.
Has it been approved?
No. The application was lapsed on 9 Jul 2025, so it is no longer under consideration.
Where is it?
In Warad, Khalapur, Raigarh, Maharashtra.
How big is it?
It has a stated cost of ₹247 crore; a site of 0.5 acres and 2.3 acres (0.9 ha) of forest land.
When was it filed?
The application was filed on 1 Jan 2024.
Project details
| Status | Lapsed |
|---|---|
| Status since | 9 Jul 2025 |
| Application filed | 1 Jan 2024 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Water & irrigation |
| Applicant | Maharashtra Jeevan Pradhikaran |
| Land area | 2,200 m² |
| Forest land | 2.3 acres (0.9 ha) |
| Project cost | ₹247 crore |
| Village / locality | Warad |
| Taluk / tehsil | Khalapur |
| District | Raigarh |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-14976 |
In context
31 applications in Raigarh since January 2022 are in the same category (Water & irrigation): 11 approved, 14 filed or under review, and 6 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 0.5 acres, this one is smaller than 97% of them.
16 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Warad, Khalapur, Raigarh, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Environment Clearance for Proposed development at Plot No. 16/5, 17/2, 17/5a,… — environmental approval granted, 1.1 km away
- Environmental Clearance for the proposed development of industrial area by… — environmental approval granted, 1.7 km away
- Environmental Clearance for the proposed development of industrial area by… — cleared for impact study, 1.7 km away
- Environmental Clearance for development of industrial area by Maharashtra… — lapsed, 1.7 km away
- Proposed 6-Lane Access Controlled Section of NH-348B (Greenfield) from Pagote… — lapsed, 2.4 km away
- Environment Clearance of construction project for proposed expansion of… — environmental approval granted, 3.8 km away
- Industrial project by M/s. LAKELAND CHEMICALS (INDIA) LIMITED (CIPM) — initial checks, 4 km away