Quick answers
What is this project?
"Diversion of 1.2442 ha of Forest land for Construction of LILO Line from Tower No. 14 of Lakhandur-Morgaon Arjuni 132 KV Line to Wadegaon TSS" is a proposed power project in Kanhalgaon, Arjuni Morgaon, Gondiya, Maharashtra. The site covers 6.9 acres.
Who is building it?
The applicant is Msetcl Ehv Construction Dn II.
Has it been approved?
Not yet. The application is still under review: its status is “In-principle approval, conditions pending”, as of 27 Nov 2026.
Where is it?
In Kanhalgaon, Arjuni Morgaon, Gondiya, Maharashtra.
How big is it?
It has a stated cost of ₹6.5 crore; a site of 6.9 acres and 3.1 acres (1.2 ha) of forest land.
When was it filed?
The application was filed on 25 Aug 2024.
Project details
| Official title | "Diversion of 1.2442 ha of Forest land for Construction of LILO Line from Tower No. 14 of Lakhandur-Morgaon Arjuni 132 KV Line to Wadegaon TSS" at Village Wadegaon Rly of Arjuni Morgaon Tahsil in District Gondia |
|---|---|
| Status | In-principle approval, conditions pending |
| Status since | 27 Jan 2026 |
| Application filed | 25 Aug 2024 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Power |
| Applicant | Msetcl Ehv Construction Dn II |
| Land area | 6.9 acres (2.8 ha) |
| Forest land | 3.1 acres (1.2 ha) |
| Project cost | ₹6.5 crore |
| Village / locality | Kanhalgaon |
| Taluk / tehsil | Arjuni Morgaon |
| District | Gondiya |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-15125 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 25 Aug 2024 (this page) | In-principle approval, conditions pending | 6.9 acres | ₹6.5 crore |
| New project filed 28 Mar 2024 | More information requested | 6.9 acres | ₹6.5 crore |
In context
7 applications in Gondiya since January 2022 are in the same category (Power): 0 approved, 6 filed or under review, and 1 withdrawn, lapsed or rejected.
1 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Kanhalgaon, Arjuni Morgaon, Gondiya, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- "Diversion of 1.2442 ha of Forest land for Construction of LILO Line from… — more information requested, 0 m away
- Environmental Clearance for proposed Mahalgaon-1 Sand Ghat (4 ha) At -Gut No.… — environmental approval granted, 2.6 km away
- Proposal for Installation of BSNL 4G Tower at Tidka Village(Village… — more information requested, 6.2 km away
- Proposal for Installation of BSNL 4G Tower at Tidka Village(Village… — more information requested, 6.2 km away
- Proposal for Installation of BSNL 4G Tower at Tidka Village(Village… — more information requested, 6.2 km away
- Environmental Clearance for proposed Singhmarhan Sand Ghat (1.05ha) At -Gut… — environmental approval granted, 10.2 km away
- Sindmarhan Sand Ghat, Gondia — environmental approval granted, 10.2 km away
- Environmental Clearance for proposed Wadegaon bandya (1.04 ha) At -Gut No.… — environmental approval granted, 13.6 km away
More from Msetcl Ehv Construction Dn II in Gondiya
- Diversion of 10.2297 ha for Construction of 132 KV Transmission Line LILO on… — more information requested
- Diversion of 10.2297 ha for Construction of 132 KV Transmission Line LILO on… — under forest review
4 Msetcl Ehv Construction projects in Gondiya
All 7 Msetcl Ehv Construction projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.