Quick answers
What is this project?
Re-diversion of 0.2082 ha. Forest land for laying underground Optical Fiber Cable of along the existing Right of Way of Pandharkawada to Saifal,Yawatmal District Border in Existing ROW of SH 314, 315 & 267 Total length 48/470 Km (Forest length 6.940 km) in Villages Deheli, Zuli Taluka Kedapur and Village Jamb, Kaleshwar, Parva, Kurli, Govindpur and Saifal Taluka Ghatanji of Yawatmal District. in the State of Maharashtra is a proposed telecom project in Sharad, Ghatanji, Yavatmal, Maharashtra. The site covers 3.6 acres.
Who is building it?
The applicant is Vodafone Idea Telecom Infrastructure Limited.
Has it been approved?
Not yet. The application is still under review: its status is “More information requested”, as of 27 Nov 2026.
Where is it?
In Sharad, Ghatanji, Yavatmal, Maharashtra.
How big is it?
It has a stated cost of ₹73 lakh; a site of 3.6 acres and 2,080 m² of forest land.
When was it filed?
The application was filed on 22 Apr 2025.
One of 2 filings for this project. The project's main page, with every filing and where each stands: Re-diversion of 0.2082 ha. Forest land for laying underground Optical Fiber Cable of…
Project details
| Official title | Proposal for re-diversion of 0.2082 ha. Forest land for laying underground Optical Fiber Cable of along the existing Right of Way of Pandharkawada to Saifal,Yawatmal District Border in Existing ROW of SH 314, 315 & 267 Total length 48/470 Km (Forest length 6.940 km) in Villages Deheli, Zuli Taluka Kedapur and Village Jamb, Kaleshwar, Parva, Kurli, Govindpur and Saifal Taluka Ghatanji of Yawatmal District. in the State of Maharashtra |
|---|---|
| Status | More information requested |
| Status since | 16 Apr 2026 |
| Application filed | 22 Apr 2025 |
| Approval sought | Forest land use |
| Application type | Change of use |
| Sector | Telecom |
| Applicant | Vodafone Idea Telecom Infrastructure Limited |
| Land area | 3.6 acres (1.5 ha) |
| Forest land | 2,080 m² |
| Project cost | ₹73 lakh |
| Village / locality | Sharad |
| Taluk / tehsil | Ghatanji |
| District | Yavatmal |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-15843 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 26 Dec 2025 | More information requested | 3.6 acres | ₹73 lakh |
| Change of use filed 22 Apr 2025 (this page) | More information requested | 3.6 acres | ₹73 lakh |
In context
32 applications in Yavatmal since January 2022 are in the same category (Telecom): 5 approved, 6 filed or under review, and 21 withdrawn, lapsed or rejected. The approved ones took a median of 2.0 years from filing to approval. At 3.6 acres, this one is larger than 53% of them.
1 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Sharad, Ghatanji, Yavatmal, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Re-diversion of 0.2082 ha. Forest land for laying underground Optical Fiber… — more information requested, 0 m away
- Diversion of Forest Land for Laying Underground Optical Fiber Cable Along Row… — lapsed, 4.6 km away
- 4G Saturation Project of GOVERNMENT OF INDIA — more information requested, 12.9 km away
- Stone quarry proposal of Mr. Anirudha Anil Gore ,Village Pangadi , Tq.… — environmental approval granted, 13.2 km away
- Diversion of forest Land Laying Underground OFC along the existing Right of… — forest land use approved, 17.6 km away
- 7-MW Solar Plant MSKVY 2.0 at Undarni (33/11KV Shiroli Substation) — lapsed, 19.2 km away
- "Diversion of Forest land for construction of Sanskrutik Bhavan Building at… — lapsed, 19.6 km away
- Revalidation of prior EC of Sand Ghat Proposal of Ayata-2 Sand Ghat Tq. Arni… — environmental approval granted, 21 km away
More from Vodafone Idea Telecom Infrastructure Limited in Yavatmal
- Re-diversion forest land for laying underground Optical fiber cable of… — forest land use approved
- Re-diversion forest land for laying underground Optical fiber cable of… — in-principle approval, conditions pending
- Re-diversion of forest land in favour of Vodafone Idea Telecom Infrastructure… — lapsed
- Diversion of forest land for laying Underground Optical Fiber Cable within RoW… — lapsed
- Re-Diversion of Forest Land in Favour of Vodafone Idea Telecom Infrastructure… — lapsed
7 Vodafone Idea Telecom projects in Yavatmal
All 71 Vodafone Idea Telecom projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.