Quick answers
What is this project?
Stone Quarry proposal of Mrs. Bindeshwaridevi Devendrasingh Rawal,Vill.-Tembhe Bu., Tq Shahada, Dist Nandurbar, Gut No. 52 Part, , Area-2.82 Ha is a proposed mining project in Tembhe Bk, Shahade, Nandurbar, Maharashtra. The site covers 7 acres.
Who is building it?
The applicant is Project Proponent.
Has it been approved?
Not yet. The application is still under review: its status is “Initial checks”, as of 27 Nov 2026.
Where is it?
In Tembhe Bk, Shahade, Nandurbar, Maharashtra.
How big is it?
It has a stated cost of ₹68 lakh and a site of 7 acres.
When was it filed?
The application was filed on 29 Oct 2026.
Project details
| Status | Initial checks |
|---|---|
| Status since | 29 Oct 2026 |
| Application filed | 29 Oct 2026 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Mining |
| Applicant | Project Proponent |
| Land area | 7 acres (2.8 ha) |
| Project cost | ₹68 lakh |
| Village / locality | Tembhe Bk |
| Taluk / tehsil | Shahade |
| District | Nandurbar |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-18016 |
In context
26 applications in Nandurbar since January 2022 are in the same category (Mining): 24 approved, 1 filed or under review, and 1 withdrawn, lapsed or rejected. The approved ones took a median of 19 days from filing to approval. At 7 acres, this one is larger than 96% of them.
No other mining lease on record has applied within 5 km of this site.
Where it is
Tembhe Bk, Shahade, Nandurbar, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Sand Ghat Proposal of Kurhawad T. Sa. Sand Ghat Tq. Shahada Dist.… — environmental approval granted, 5 km away
- Transfer of Environmental Clearance of Arale Sandghat, Gut No. 180, 181, Area… — environmental approval granted, 5.3 km away
- Sand Ghat Proposal of Arale Sand Ghat Tq. Nandurbar Dist. Nandurbar,Nearest… — environmental approval granted, 5.3 km away
- Sand Ghat Proposal of Arale Sand Ghat Tq. Nandurbar Dist. Nandurbar,Nearest… — environmental approval granted, 5.5 km away
- Sand Ghat proposal of Kauthal T. Sa. Sand Ghat Tq. Shahada Dist.… — environmental approval granted, 6.1 km away
- Transfer of Environmental Clearance of Kavthal T. Sa. Sandghat, Gut No. 1/1,… — environmental approval granted, 6.6 km away
- Sand Ghat Proposal of Kavthal T. Sa. Sand Ghat Tq. Shahada Dist. Nandurbar,… — environmental approval granted, 6.6 km away
- Transfer of Environmental Clearance of Osarli Sandghat, Gut No. 8/3, 9, 10,… — environmental approval granted, 7.3 km away
More from Project Proponent in Nandurbar
- Stone quarry proposal of M/s D. G. Chavhan & Company,Prop. Dilip Gulabrao… — environmental approval granted
- Stone Quarry proposal of Mr. Ashok Ramdas Patil Vill.-Dongargaon, Tq Shahada,… — environmental approval granted
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.