Project details
| Official title | Construction of NEEPCO Township at Umsawli, Mawdiangdiang, New Shillong, Meghalaya |
|---|---|
| Status | Initial checks |
| Status since | 24 Nov 2026 |
| Application filed | 11 Nov 2026 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Buildings & townships |
| Applicant | North Eastern Electric Power Corporation LTD |
| Land area | 21.7 acres (8.8 ha) |
| Project cost | ₹166.5 crore |
| Village / locality | Mawlong |
| Taluk / tehsil | Mylliem |
| District | East Khasi Hills |
| State | Meghalaya |
| Location from | Site boundary on record |
| Our reference | WID-ML-00408 |
What the filings say
What is planned
North Eastern Electric Power Corporation Limited (NEEPCO) proposes to develop a residential and institutional campus at New Shillong. The project, planned on a plot of 87,654.91 square metres (21.66 acres), will have a total built-up area of 26,446.74 square metres. The applicant's project report states that no construction has yet commenced at the site.
The township is designed to include 22 main building blocks with a maximum height of G+3 floors (13.8 metres). The residential component consists of 85 dwelling units and 55 hostel rooms. The building configuration includes:
- Housing blocks (13 blocks): 61 Executive Family units, 4 Supervisor Family units, and 20 Workmen Family units.
- Hostel blocks (3 blocks): 20 Executive rooms, 4 Supervisor rooms, and 31 Workmen rooms.
- Community buildings (3 blocks): Including a guest house with 8 rooms, a shopping complex with a hall and cafeteria, and a multipurpose indoor complex.
- Utility buildings (3 blocks): Gateways, watch towers, and service rooms.
The estimated population for the township is 954 persons, comprising 551 residents, 43 staff members, and 360 visitors.
Layout and design
The master plan integrates the hilly terrain, which has a level difference of approximately 23 metres between its highest and lowest points. A natural stream (nala) crosses the site; the applicant proposes to preserve and strengthen it with an RCC channel. Internal roads will cross the stream via two RCC box culverts, while pedestrians will use two foot-over bridges.
Open spaces are a significant component of the layout, with 23,140 square metres (26.4% of the plot area) dedicated to green and landscape areas. Recreational facilities include a futsal ground, lawn tennis court, basketball court, and badminton courts. The project also features an existing pond that will be retained and beautified for water storage.
Land and surroundings
The project site is vacant government land leased from the New Shillong Township Development Agency (NSTDA). The land use is earmarked as residential and institutional in the New Shillong Master Plan. While the site is currently undeveloped, it contains a pre-existing house at the eastern part which will be retained.
A survey identified 2,214 existing trees on the property. The applicant has obtained permission to fell 1,052 trees, while 1,162 trees will be retained. To compensate for the felling, 10,520 trees are required for plantation; 660 will be planted within the project site, and the remaining 9,860 will be planted elsewhere.
Water, power and access
Water: The total water requirement is estimated at 209 kilolitres per day (kld). Fresh water demand of 56 kld will be met through onsite tubewells. The remaining 153 kld will be sourced from recycled treated effluent for flushing and horticulture. An onsite Sewage Treatment Plant (STP) with a capacity of 90 kld is proposed, using Sequential Batch Reactor (SBR) technology. The project aims for Zero Liquid Discharge (ZLD).
Power: The demand load is 614 kW, to be supplied by the Meghalaya Power Distribution Corporation Ltd (MePDCL). For backup, two diesel generator sets of 400 kVA each (total 800 kVA) will be installed. The project also includes solar photovoltaic panels with a capacity of 65 kWp, intended to meet 10.6% of the demand load.
Access: The site is adjacent to the NEEPCO Township Road on the east. It is located approximately 6.35 km from National Highway 6 and 8.07 km from Shillong Airport (Umroi).
Environmental safeguards
The applicant proposes several conservation measures:
- Rainwater Harvesting: 18 recharge pits are planned to collect rooftop runoff, with a total retention volume of 339 cubic metres.
- Waste Management: Solid waste is estimated at 357 kg/day. Organic waste (168 kg/day) will be treated in an onsite Organic Waste Converter (OWC) with a capacity of 500 kg/day. Recyclable dry waste will be sold to authorized recyclers.
- Energy Efficiency: Measures include LED lighting, photoelectric sensors for outdoor lights, and thermal insulation for roofs.
| Item | Detail |
|---|---|
| Total Plot Area | 8.77 hectares (21.66 acres) |
| Total Built-up Area | 26,446.74 sqm |
| Proposed Ground Coverage | 10,891.70 sqm (12.43%) |
| Total Parking Proposed | 230 ECS |
| EV Charging Points | 46 nos. |
| STP Capacity | 90 kld |
| Solar Panel Capacity | 65 kWp |
| Estimated Project Cost | ₹166.48 crore |
NEEPCO Township at Umsawli, Mawdiangdiang, New Shillong, Meghalaya site plan and layout
4 drawings from the project's filings. Sign in free to see them.
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see itIn context
6 applications in East Khasi Hills since January 2022 are in the same category (Buildings & townships): 1 approved, 2 filed or under review, and 3 withdrawn, lapsed or rejected.
1 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Mawlong, Mylliem, East Khasi Hills, Meghalaya. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Unity Mall and Infrastructure at New Shillong Township, Umsawli, Shillong by… — lapsed, 1.6 km away
- Faculty Apartment for 12 (Twelve) Units at NEHU, Permanent Campus Shillong — forest land use approved, 5.4 km away
- 96 (Ninety Six) Seated Girls Hostel including Warden's Residence at NEHU,… — forest land use approved, 5.7 km away
- Cluster of Class Room for Sciences at NEHU, Permanent Campus Shillong — forest land use approved, 6.1 km away
- 96 (Ninety Six) Seated Boys Hostel including Warden's Residence at NEHU,… — forest land use approved, 6.6 km away
- Cluster of Class Room for Other than Sciences at NEHU, Permanent Campus Shillong — forest land use approved, 6.8 km away
- Phudmawri Water Supply Scheme — forest land use approved, 8 km away
- Renewal of Lease for Plot of Land to Shillong Higher Secondary School — lapsed, 8.1 km away
All 11 North Eastern Electric Power Corporation projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.